Example project plan

Project plan for a website relaunch

A website relaunch project plan can organize a bilingual corporate site rebuild into 10 phases, 63 tasks, 20 weeks, and an approximate €230,500 budget. This PathHub AI example covers governance, content architecture, accessible design, CMS and PIM integration, EU hosting, SEO migration, localization, compliance, stakeholders, and risks.

  • 20 Weeks
  • 10 Phases
  • 63 Tasks
  • Budget approx. €230,500

No sign-up · opens instantly

Your own project? The AI project plan generator builds a plan like this from a short description.

This is how the plan looks in PathHub. Pick a tab or open the plan live to tick off tasks and edit everything.

app.pathhub.ai/try?example=web-enOpen live
PathHub view “Overview” of the example plan Corporate Website Relaunch for Industrial Supplier
Progress, time, budget, risks and obligations at a glance, plus the next tasks and AI hints.

The plan in detail

Everything in the example plan to read through. In the live plan you can take it over and adapt it.

Phases and tasks

Phase 1: Discovery, Governance and Requirements

Week 1–2 · 5 tasks · Owner: Executive Sponsor / Managing Director

Establish the project framework, confirm business and technical requirements, and align all departments on scope, decision rights, and success criteria. This creates a controlled foundation for the CMS, PIM, content, compliance, and migration workstreams.

  • Establish the project governance model, decision rights, working groups, approval gates, and escalation processProject Manager · 2 days
  • Important Conduct requirements workshops with Marketing, Product Management, Sales, HR, IT, Legal, SEO, and content representativesProject Manager · 4 days
  • Document functional and non-functional requirements for the bilingual website, CMS, PIM catalogue, careers section, accessibility, SEO, analytics, and EU hostingBusiness Analyst · 5 days
  • Create the approved scope baseline, stakeholder register, dependency log, success metrics, and initial delivery planProject Manager · 3 days
  • Important Implement ePrivacy-compliant consent management for non-essential cookies, analytics, advertising tags, and similar technologies, including prior consent where required, an equally prominent refusal option, consent …Legal, Data Protection Officer and SEO/Analytics Owner · 3 days

Phase 2: Information Architecture and Content Model

Week 3–5 · 7 tasks · Owner: Marketing and Corporate Communications

Define how corporate, product, careers, service, contact, and download content will be organized and maintained in German and English. The phase establishes the navigation, taxonomy, metadata, URL principles, and CMS/PIM content relationships required for design and implementation.

  • Important Create the target sitemap covering corporate information, industries, products, services, downloads, careers, contact, legal content, and language switchingInformation Architect · 4 days
  • Define product taxonomy, product families, filters, technical attributes, units, document types, and category relationships with Product ManagementProduct Management and Product Data Owners · 5 days
  • Design the CMS content model for pages, news, downloads, locations, contacts, forms, careers content, legal pages, and reusable componentsCMS Solution Architect · 5 days
  • Define German-English language relationships, translation statuses, fallback rules, terminology ownership, and publishing dependenciesContent Editor Lead · 3 days
  • Important Define the URL, slug, canonical, metadata, and breadcrumb rules for corporate and product contentSEO and Analytics Owner · 3 days
  • Specify search, filtering, faceting, document discovery, and enquiry journey requirements for customer-facing product contentSales and Customer Service · 3 days
  • Important Meet the project’s WCAG 2.1 AA target and assess alignment with EN 301 549 and applicable European or national accessibility obligations, including accessible templates, forms, navigation, multimedia, PDFs, product …UX Lead, QA Lead, Legal and Content Owners · 3 days

Phase 3: UX and Visual Design

Week 5–8 · 6 tasks · Owner: Marketing and Corporate Communications

Translate the approved structure into accessible, responsive user journeys and visual patterns. Designs will cover the most important corporate, product, careers, contact, form, search, and download experiences before development begins.

  • Create accessible user journeys for product discovery, product comparison or enquiry, document downloads, contact requests, careers browsing, and language switchingUX Designer · 5 days
  • Produce low-fidelity wireframes for the homepage, corporate pages, product listing, product detail, search results, careers pages, forms, downloads, and contact pagesUX Designer · 6 days
  • Important Define the accessible design system, including typography, color contrast, focus states, keyboard behavior, error states, component semantics, and responsive breakpointsAccessibility Specialist · 4 days
  • Create high-fidelity responsive designs for desktop, tablet, and mobile page templates in German and English contextsUI Designer · 7 days
  • Design reusable components for navigation, product filters, technical data tables, document cards, calls to action, forms, alerts, and careers vacancy cardsUI Designer · 5 days
  • Validate designs with Marketing, Product Management, Sales, HR, and representative content editors and incorporate consolidated feedbackUX Lead · 4 days

Phase 4: Technical Architecture and Hosting Setup

Week 6–8 · 6 tasks · Owner: IT and Enterprise Architecture

Establish the technical foundation for the new platform, including CMS architecture, environments, EU hosting, security, deployment, monitoring, and integration principles. Decisions made here reduce implementation and operational risks later in the project.

  • Confirm the CMS architecture, hosting model, environments, deployment workflow, backup approach, monitoring, and support boundariesIT and Enterprise Architecture · 4 days
  • Important Provision EU-based development, staging, and production hosting environments with network controls, TLS certificates, backups, and recovery settingsEU Hosting, Security and Operations Provider · 5 days
  • Define CMS roles, editorial permissions, approval workflows, authentication requirements, and access review proceduresIT and Enterprise Architecture · 3 days
  • Specify CMS, PIM, careers, search, forms, analytics, consent management, and document storage integration interfacesTechnical Architect · 4 days
  • Complete the GDPR, cookie, form-processing, data-retention, subprocessor, and EU hosting assessmentData Protection, Legal and Compliance · 4 days
  • Create the environments, deployment, logging, monitoring, incident response, and rollback runbooksEU Hosting, Security and Operations Provider · 4 days

Phase 5: CMS Implementation and Core Integrations

Week 8–12 · 10 tasks · Owner: External CMS/PIM Implementation Partner

Configure and develop the CMS foundation, reusable frontend components, editorial workflows, search, forms, consent handling, and core corporate website functionality. The implementation will follow the approved design system and content model.

  • Configure CMS projects, content types, reusable fields, language handling, publishing states, versioning, and editorial workflowsCMS Implementation Partner · 6 days
  • Important Develop the responsive frontend shell, global navigation, header, footer, breadcrumbs, language switcher, and accessibility-ready component frameworkFrontend Lead Developer · 8 days
  • Implement corporate page templates for the homepage, company profile, locations, industries, services, news, downloads, and contact contentCMS Implementation Partner · 7 days
  • Implement accessible search, autocomplete, result ranking, filters, no-result handling, and product/content result presentationSearch Engineer · 6 days
  • Configure contact, product enquiry, callback, and download forms with validation, notifications, spam protection, and consent captureFull-Stack Developer · 5 days
  • Integrate the consent management platform and configure consent-aware analytics and marketing tagsTechnical Architect · 4 days
  • Configure media, document, image, and download asset handling with file metadata, language variants, alt-text fields, and usage controlsCMS Implementation Partner · 4 days
  • Implement editorial preview, approval, scheduled publishing, unpublishing, and audit-trail functionalityCMS Implementation Partner · 4 days
  • Connect approved corporate analytics events, form conversions, internal search tracking, and download trackingSEO and Analytics Owner · 4 days
  • Complete developer-level testing of templates, components, forms, search, language switching, and editorial workflowsQA Lead · 5 days

Phase 6: PIM Product Catalogue Integration

Week 11–14 · 7 tasks · Owner: Product Management and Product Data Owners

Connect the PIM to the CMS or catalogue presentation layer and implement the product browsing experience. Product data, technical attributes, documents, assets, units, and German-English relationships will be validated before publication.

  • Important Map PIM entities, product families, attributes, units, documents, images, translations, statuses, and identifiers to the approved CMS and frontend modelPIM Solution Architect · 6 days
  • Implement the PIM API or middleware connection, authentication, synchronization schedule, error handling, and loggingIntegration Engineer · 8 days
  • Develop product listing, category, product detail, technical data, document, related-product, and enquiry componentsFrontend Lead Developer · 7 days
  • Configure product search, filters, facets, sorting, availability or status indicators, and language-specific resultsSearch Engineer · 5 days
  • Validate product assets, document links, image renditions, technical units, mandatory fields, and product lifecycle statusesProduct Data Owners · 5 days
  • Important Reconcile German and English product data, identify missing translations, and create a remediation list with named owners and deadlinesContent Editor Lead · 4 days
  • Execute catalogue integration testing using representative product families and confirm synchronization, display, filtering, enquiry, and error scenariosQA Lead · 5 days

Phase 7: Careers, Content Migration and Localization

Week 12–15 · 7 tasks · Owner: Marketing and Corporate Communications

Implement the careers area and migrate approved corporate content into the new CMS while completing German-English localization. Content ownership, quality, legal review, and PIM-related product content gaps will be resolved before final QA.

  • Implement careers landing pages, job listings, job detail pages, department or location pages, application calls to action, and employer-brand content templatesCMS Implementation Partner · 6 days
  • Connect the careers section to the approved vacancy feed or recruitment interface and define the manual fallback processHR and Recruiting · 4 days
  • Important Create the content inventory and migration tracker covering every existing corporate URL, content owner, language version, target template, status, and migration decisionContent Migration Lead · 5 days
  • Migrate approved German corporate content, downloads, media, legal pages, contact details, and location information into the CMSContent Editors and Country or Language Representatives · 7 days
  • Translate or review English content and align German-English terminology across corporate, product-supporting, careers, and legal contentLocalization Lead · 7 days
  • Migrate or coordinate product descriptions, technical documents, and supporting assets that are not supplied directly by the PIMProduct Data Owners · 5 days
  • Complete editorial review for factual accuracy, links, documents, metadata, image alt text, ownership, and publishing statusMarketing and Corporate Communications · 5 days

Phase 8: Accessibility, SEO and Quality Assurance

Week 14–16 · 7 tasks · Owner: QA Lead

Verify that the complete website meets the agreed WCAG 2.1 AA target, preserves organic search value, performs reliably, and complies with security, privacy, browser, and analytics requirements. Defects will be prioritized and remediated before acceptance testing.

  • Important Conduct automated and manual WCAG 2.1 AA testing across templates, navigation, forms, search, product tables, downloads, careers pages, and language switchingAccessibility Specialist · 5 days
  • Test keyboard navigation, screen-reader behavior, focus management, headings, labels, error messages, contrast, zoom, reflow, and accessible document handlingAccessibility Specialist · 4 days
  • Create the URL migration map from legacy URLs to target URLs and identify redirects, retained URLs, removed content, and replacement pagesSEO and Analytics Owner · 4 days
  • Important Implement and test 301 redirects, canonicals, hreflang, XML sitemaps, robots directives, metadata, structured data, pagination, and indexation controlsSEO and Analytics Owner · 5 days
  • Execute functional, integration, responsive, browser, device, performance, form-delivery, search, PIM synchronization, and careers-feed testingQA Lead · 6 days
  • Conduct security validation covering authentication, permissions, forms, uploads, APIs, dependencies, headers, logging, and vulnerability remediationIT and Enterprise Architecture · 4 days
  • Validate consent behavior, analytics events, form data handling, retention settings, privacy links, and legal contentData Protection, Legal and Compliance · 3 days

Phase 9: User Acceptance, Training and Launch Readiness

Week 17–18 · 4 tasks · Owner: Project Manager

Obtain formal business acceptance from the departments that own the website, train editors and administrators, and confirm that all operational and launch prerequisites are complete. No production release will proceed without documented approval and rollback readiness.

  • Important Run structured user acceptance testing with Marketing, Product Management, Sales, HR, Legal, IT, and language representatives using approved business scenariosProject Manager · 5 days
  • Resolve UAT defects, content corrections, product-data issues, translation gaps, and approval comments and retest affected functionalityExternal CMS/PIM Implementation Partner · 4 days
  • Train CMS editors, product data owners, HR users, approvers, and administrators on publishing, translations, assets, forms, careers, and issue escalationCMS Implementation Partner · 3 days
  • Important Approve the launch checklist, final content freeze, migration runbook, redirect file, analytics validation plan, rollback plan, support rota, and go-live decision recordIT and Enterprise Architecture · 3 days

Phase 10: Launch and Stabilization

Week 19–20 · 4 tasks · Owner: IT and Enterprise Architecture

Execute the controlled production cutover, validate the live website, monitor search and business-critical functionality, and resolve launch defects. Ownership will then transfer to the operational teams with documented support and monitoring procedures.

  • Execute the production deployment, final content synchronization, DNS or routing change, redirect activation, cache configuration, and smoke-test sequenceEU Hosting, Security and Operations Provider · 2 days
  • Important Validate live forms, PIM product data, careers vacancies, German-English switching, consent behavior, analytics, accessibility-critical journeys, redirects, and indexation controlsQA Lead · 3 days
  • Monitor uptime, performance, errors, search visibility, crawl activity, redirects, analytics, form submissions, product synchronization, and user feedbackSEO and Analytics Owner · 5 days
  • Resolve priority launch defects, complete the operational handover, document known issues, and obtain stabilization sign-offProject Manager · 5 days

Budget

ItemQuantityUnit priceTotal
Discovery, Governance, Information Architecture and UX
Senior Project Manager14 Person days€900€12,600
Business Analyst / Requirements Consultant10 Person days€950€9,500
Information Architect / Content Modeler8 Person days€900€7,200
UX/UI Designer14 Person days€850€11,900
Accessibility UX Reviewer3 Person days€900€2,700
CMS, PIM and Technical Integration
Solution Architect8 Person days€1,200€9,600
Senior CMS Developer28 Person days€900€25,200
Frontend Component Developer18 Person days€800€14,400
PIM Integration Engineer25 Person days€950€23,750
DevOps and Security Engineer8 Person days€950€7,600
Content Migration, Careers and Localization
Content Migration Specialist15 Person days€750€11,250
German-English Localization Editor24 Person days€600€14,400
Product Data Quality Coordinator10 Person days€750€7,500
Careers and Recruitment Integration Specialist10 Person days€850€8,500
Accessibility, SEO, Security and Quality Assurance
QA Lead14 Person days€850€11,900
Browser, Device and Regression Testers12 Person days€600€7,200
WCAG 2.1 AA Accessibility Specialist8 Person days€1,000€8,000
SEO Migration Consultant10 Person days€950€9,500
GDPR and Security Test Consultant5 Person days€1,100€5,500
Hosting Setup, Training and Go-Live
EU Hosting Environment Setup and Hardening1 Flat rate€6,500€6,500
Deployment, Monitoring and Backup Configuration1 Flat rate€4,500€4,500
CMS Editor and Administrator Training3 Person days€850€2,550
Launch and Cutover Support8 Person days€850€6,800
Operational Handover Documentation1 Flat rate€1,950€1,950
Sum of items€230,500

Risks

Product Data Quality and Regulatory Attribute Gaps

High impact

If more than 5% of sampled products have missing technical attributes, inconsistent units, incorrect classifications, outdated documents, or incomplete German-English data during Weeks 11–14, the catalogue may display inaccurate information and delay launch.

Countermeasure: Product Management and Product Data Owners will define mandatory attributes, units, validation rules, and approved regulatory claims by Week 5; the implementation partner will complete a representative data-quality audit and obtain product-owner sign-off by Week 14.

CMS and PIM Integration Failure

High impact

If the PIM API specification, ownership model, or synchronization rules are not approved by Week 8, or if two consecutive integration test cycles fail during Weeks 11–13, product pages, assets, filters, or availability information may not render reliably.

Countermeasure: IT, the implementation partner, and Product Data Owners will approve interface specifications, error handling, monitoring, and reconciliation procedures by Week 8, then complete end-to-end and failure-recovery testing before the Week 14 integration milestone.

SEO Visibility Loss During URL Migration

High impact

If the URL inventory and redirect map are incomplete, or redirect, canonical, sitemap, and indexation tests show less than 99% coverage by Week 16, the launch may cause ranking losses, broken links, and reduced organic traffic.

Countermeasure: The SEO and Analytics Owner will create and approve a page-level URL and redirect register by Week 12; the implementation partner will implement and crawl-test redirects, canonicals, robots rules, XML sitemaps, and structured data before the Week 18 go-live authorization.

WCAG 2.1 AA and Accessible Document Non-Compliance

High impact

If automated and manual testing identifies unresolved Level A or serious Level AA issues in navigation, forms, search, product filters, PDFs, careers workflows, or third-party components during Weeks 14–16, redesign and legal or reputational exposure may delay launch.

Countermeasure: The UX Lead and QA Lead will apply accessible design patterns from Week 5, test with keyboard navigation, screen readers, contrast tools, and representative assistive technologies by Week 16, and require documented remediation or risk acceptance before UAT.

GDPR, Consent and EU Hosting Misconfiguration

High impact

If data flows, processor agreements, sub-processors, retention rules, consent settings, or hosting access locations remain unapproved by Week 16, contact forms, careers applications, analytics, or cookies may process personal data unlawfully.

Countermeasure: The Data Protection Officer, Legal, IT, and the hosting provider will complete a processing inventory, DPIA screening, DPA/subprocessor review, consent test, retention design, and EU-region hosting validation by Week 16, with production access restricted and logged before launch.

Bilingual Content and Terminology Inconsistency

Medium impact

If priority German and English pages, product attributes, legal text, or careers content are not fully translated and reviewed by Week 15, users may receive contradictory technical, commercial, or employment information.

Countermeasure: Marketing, Product Data Owners, HR, and designated language representatives will approve a bilingual glossary and translation ownership model by Week 5; all priority content will receive independent language review and completeness sign-off by Week 15.

Careers and Recruitment Integration Dependency

Medium impact

If the careers feed, ATS interface, application links, consent wording, or tracking integration has not passed HR and technical testing by Week 13, vacancies may be missing, duplicated, outdated, or forced into a manual process at launch.

Countermeasure: HR and IT will confirm the ATS interface, data fields, update frequency, privacy notices, and fallback process by Week 8; the implementation partner will complete feed failure, accessibility, security, and end-to-end application tests by Week 15.

Stakeholder Approval and Content Ownership Delays

Medium impact

If product, sales, HR, legal, country, or language reviewers miss the agreed three-business-day review window during Weeks 12–17, conflicting feedback or unowned pages may prevent formal acceptance and compress launch testing.

Countermeasure: The Project Manager will publish a decision and approval matrix by Week 2, assign named owners for every priority page by Week 5, and escalate overdue or conflicting decisions to the Executive Sponsor within two business days.

Security, Backup and Operational Readiness Gaps

High impact

If penetration testing identifies unresolved high-severity vulnerabilities, or if backup restoration, monitoring, deployment, rollback, and incident-response rehearsals fail by Week 18, launch defects could cause downtime or loss of editorial and product data.

Countermeasure: IT, the hosting provider, and the implementation partner will complete vulnerability testing, patching, backup restoration, monitoring setup, access reviews, rollback rehearsal, and operational runbook approval before the Week 18 go-live decision.

Scope Growth and Budget or Timeline Compression

Medium impact

If new product templates, integrations, languages, content volumes, accessibility remediation, or stakeholder requests increase approved scope by more than 10% after Week 5, the 12% reserve may be consumed before QA and launch readiness.

Countermeasure: The Project Manager and Executive Sponsor will baseline scope, budget, and acceptance criteria in Week 2, apply formal change control from Week 3, review forecast and reserve consumption weekly, and defer or separately fund non-critical requests before Week 14.

Stakeholders

Executive Sponsor / Managing Director

Owns business outcomes, budget, scope escalation, and final go-live approval

Involve: Phase 1

Marketing and Corporate Communications

Owns corporate messaging, brand consistency, campaign priorities, and editorial governance

Involve: Phase 1

Product Management and Product Data Owners

Define product taxonomy, catalogue requirements, technical attributes, and data quality standards

Involve: Phase 1

Sales and Customer Service

Validate customer journeys, product discovery, enquiries, downloads, and regional requirements

Involve: Phase 2

Human Resources and Recruiting

Owns careers content, vacancies, application journeys, and employer-brand requirements

Involve: Phase 2

IT and Enterprise Architecture

Approves CMS integration, identity and access, environments, security, support model, and technical operations

Involve: Phase 1

Data Protection, Legal and Compliance

Reviews GDPR, cookies, forms, tracking, hosting arrangements, legal notices, and accessibility obligations

Involve: Phase 1

SEO and Analytics Owner

Defines migration rules, measurement requirements, redirects, search visibility controls, and reporting

Involve: Phase 1

Content Editors and Country or Language Representatives

Produce, review, translate, and maintain German and English content

Involve: Phase 2

External CMS/PIM Implementation Partner

Delivers architecture, development, integration, migration support, and technical remediation

Involve: Phase 1

EU Hosting, Security and Operations Provider

Implements hosting, monitoring, backups, deployment, incident response, and operational handover

Involve: Phase 4

Obligations and compliance

RequirementOwnerTimingType
Complete a GDPR processing inventory covering contact forms, analytics, cookies, careers applications, hosting, PIM/CMS integrations, recipients, retention periods, data-subject rights, and processor agreements; complete DPIA screening where required.Data Protection Officer, Legal and ITWeeks 1–16; ongoing after launchMandatory
Implement ePrivacy-compliant consent management for non-essential cookies, analytics, advertising tags, and similar technologies, including prior consent where required, an equally prominent refusal option, consent records, and withdrawal functionality.Legal, Data Protection Officer and SEO/Analytics OwnerWeeks 8–16; ongoing monitoringMandatory
Protect applicant and employee-related data in the careers section through lawful-basis and privacy notices, role-based access, restricted data collection, retention and deletion rules, secure transmission, and approved ATS processors.HR, Data Protection Officer and ITWeeks 7–16; ongoingMandatory
Meet the project’s WCAG 2.1 AA target and assess alignment with EN 301 549 and applicable European or national accessibility obligations, including accessible templates, forms, navigation, multimedia, PDFs, product documents, and third-party components.UX Lead, QA Lead, Legal and Content OwnersWeeks 3–18; ongoing content governanceMandatory
Publish accurate German and English legal disclosures, including provider identification/imprint, privacy information, cookie information, contact details, and applicable terms or disclaimers for digital services.Legal and MarketingWeeks 10–17; review on material changeMandatory
Host production and backup environments in approved EU regions, document subprocessors and support access locations, enforce encryption, least-privilege access, logging, vulnerability management, backups, restoration testing, and incident-response procedures.IT, Enterprise Architecture and Hosting ProviderWeeks 6–18; ongoing operationsImportant
Apply internal security and operational standards, including OWASP-based application testing, browser and device compatibility testing, release approvals, accessibility and SEO evidence, analytics validation, monitoring, rollback procedures, and formal go-live sign-off.QA Lead, IT, Implementation Partner and Project ManagerWeeks 14–20; ongoing release managementImportant

Milestones

WeekMilestonePrerequisite
2Approved requirements baseline, governance model, scope, success criteria, and delivery planDiscovery, governance, and stakeholder alignment
5Approved sitemap, content model, product taxonomy, bilingual content rules, search requirements, and URL principlesRequirements baseline and content governance
8Approved accessible design system, responsive templates, and validated user journeys for all priority content typesInformation architecture and content model
8Approved technical architecture with operational EU environments, security controls, integration specifications, and compliance decisionsArchitecture and hosting setup
12CMS-enabled corporate website foundation with tested templates, workflows, search, forms, consent management, and analytics instrumentationTechnical architecture and CMS implementation
14Validated PIM-to-website integration with approved product taxonomy, representative catalogue data, bilingual product content, and tested product journeysCMS foundation and product data readiness
15Careers functionality operational and all priority German-English content migrated, reviewed, assigned to owners, and ready for formal QAPIM integration and content localization
16Signed QA report showing resolved critical defects, WCAG remediation status, tested SEO migration controls, and approved security and compliance resultsContent migration and implemented functionality
18Signed business acceptance, trained operational users, approved launch checklist, and formal go-live authorizationQA completion and launch readiness
20Website live in German and English with validated redirects, integrations, monitoring, operational handover, and stabilization sign-offGo-live authorization and launch execution

How this plan was created

This plan was created by PathHub AI from a single description: “Relaunch the corporate website of an industrial supplier with 300 employees in German and English: new CMS, product catalogue from the PIM, careers section, accessibility to WCAG 2.1 AA, SEO migration of existing URLs and hosting in the EU.” Without company context. With your departments, approval processes and compliance requirements it becomes much more precise.

Obligations

Obligations with lead time: what many think of too late

These obligations are typically triggered by a website relaunch (example: Germany). PathHub AI schedules them with lead time, warns when the schedule is too tight and shows the rule with its criteria under “Rule & evidence”, which you tick off and back with evidence. Not legal advice.

Privacy policy, consent management for cookies/tracking (Sec. 25 TDDDG) and agreements with used services before go-live
Required 1–3 weeks before go-livestatutory
Rule & evidence

Why: Every website with analytics, maps, video or marketing services processes personal data.

Legal basis: Sec. 25 TDDDG: consent before setting non-essential cookies and trackers; GDPR Art. 13 information from the first visit.

Rule from the compliance library
Telecommunications Digital Services Data Protection Act (TDDDG, formerly TTDSG)
Criteria
  • Cookie consent banner for all non-essential cookies and trackers
  • Active opt-in without pre-ticked boxes
  • Rejecting as easy as accepting
  • Consent withdrawal available at any time

If breached: TDDDG fines up to €300,000. GDPR fines up to €20m or 4% apply in parallel.

Evidence: In PathHub you tick off the criteria and attach evidence to each item as a file, link or note. Everything exports as a PDF evidence report.
Check accessibility of shop and checkout and publish an accessibility statement (BFSG)
Important 4–8 weeks before go-livestatutory
Rule & evidence

Why: Accessibility has been mandatory for online shops serving consumers since June 2025.

Applies: if consumers can conclude contracts online (e.g. shop, booking); micro-enterprises with fewer than 10 employees and at most EUR 2m turnover or balance sheet are exempt for services

Legal basis: The BFSG has applied since 28 June 2025 to e-commerce services for consumers.

Rule from the compliance library
Accessibility Strengthening Act (BFSG)
Criteria
  • Accessibility of certain products and services (e.g. e-commerce, banking, e-books) since 28 June 2025
  • Compliance with accessibility requirements (perceivability, operability, understandability, robustness)
  • Provision of accessibility information for consumers
  • Micro-enterprise exemption for services (fewer than 10 employees and at most €2m turnover)

If breached: Fine up to €100,000 per violation. Sales ban until remediated.

Evidence: In PathHub you tick off the criteria and attach evidence to each item as a file, link or note. Everything exports as a PDF evidence report.
Implement mandatory information, withdrawal notice, price display and order button correctly
Important 1–2 weeks before go-livestatutory
Rule & evidence

Why: Distance-selling errors are a frequent reason for warning letters and extend withdrawal periods.

Applies: when selling to consumers

Rule from the compliance library
Distance Selling Law
Criteria
  • Pre-contractual information obligations for distance contracts (Art. 246a EGBGB)
  • Proper cancellation policy and provision of the model withdrawal form
  • 14-day right of withdrawal for consumers
  • Clearly designed ordering process with the "button solution" (order with obligation to pay)
  • Transparent information on total price, delivery/shipping costs and contract term

If breached: Warnings and injunctions by competitors/consumer associations. Fines up to €250,000.

Evidence: In PathHub you tick off the criteria and attach evidence to each item as a file, link or note. Everything exports as a PDF evidence report.
Register in the LUCID packaging register and license packaging with a scheme
Important 1–2 weeks before go-livestatutory
Rule & evidence

Why: Without registration, selling is prohibited.

Applies: if packaged goods are shipped to private end consumers

Legal basis: Packaging Act: registration in the LUCID register and system participation before first placing on the market.

Rule from the compliance library
Packaging Act
Criteria
  • Registration in the LUCID packaging register before placing on the market
  • System participation (licensing) of sales packaging subject to participation with a dual system
  • Identical volume reporting to LUCID and the dual system
  • Declaration of completeness when statutory volume thresholds are exceeded
  • Observance of take-back and deposit obligations (e.g. one-way deposit)

If breached: Sales and distribution ban for non-registration. Fines up to €200,000.

Evidence: In PathHub you tick off the criteria and attach evidence to each item as a file, link or note. Everything exports as a PDF evidence report.
All typical initiatives and their obligations: planning internal projects

Frequently asked questions

How long does a website relaunch take?
In the example plan, a website relaunch takes 20 weeks in 10 phases, of which 6 phases partly run in parallel. The actual duration depends on company size, starting point and available resources, with your company context PathHub adjusts the schedule accordingly.
What does a website relaunch cost?
The example plan estimates about €230,500, split into 24 budget line items with quantity and unit price. The largest items are CMS, PIM and Technical Integration, Discovery, Governance, Information Architecture and UX. This is an AI estimate as a starting point, not a quote.
What are the risks of a website relaunch?
The plan lists 10 risks with countermeasures. Rated highest: Product Data Quality and Regulatory Attribute Gaps; CMS and PIM Integration Failure; SEO Visibility Loss During URL Migration.
Who needs to be involved in a website relaunch?
Among others, the plan includes these people: Executive Sponsor / Managing Director, Marketing and Corporate Communications, Product Management and Product Data Owners, Sales and Customer Service, Human Resources and Recruiting, IT and Enterprise Architecture. For each role it states why and from when to involve them.
Can I adapt the plan to my company?
Yes. Open the plan in PathHub without signing up, adjust phases and tasks or describe your own initiative: with company context (departments, approval processes, works council, compliance requirements) every further plan gets more precise.