Example project plan

Project plan for a website relaunch

A website relaunch involves marketing, sales, HR and IT — and without a clean SEO migration it puts years of search visibility at risk. This plan shows the relaunch of a bilingual corporate website with product catalogue, careers section and accessibility.

No sign-up · opens instantly · 20 Weeks · 10 Phases · 61 Tasks · Budget approx. €230,500

This is how the plan looks in PathHub — click through the tabs or tick off tasks.

app.pathhub.ai/try?example=web-enOpen live
Example plan

Corporate Website Relaunch for Industrial Supplier

Relaunch the corporate website of an industrial supplier in German and English with a new CMS, integrated product catalogue from the PIM, and a dedicated careers section. The project must preserve SEO value during URL migration, meet WCAG 2.1 AA accessibility requirements, and operate on EU-based hosting infrastructure. It also requires coordinated content migration, localization, and governance across marketing, product, HR, IT, legal, and external implementation partners. The outcome should be a modern, compliant, and maintainable platform that supports customer discovery, recruiting, and corporate communications.

Total Progress0%
20Weeks
0/10Phases
0/61Tasks
€230,500Budget
AI Recommendations KIAI Chat KIAI Tools KI

Phases

1

Phase 1: Discovery, Governance and Requirements

Pending · 2W · 0/4
Executive Sponsor / Managing Director
0

Establish the project framework, confirm business and technical requirements, and align all departments on scope, decision rights, and success criteria. This creates a controlled foundation for the CMS, PIM, content, compliance, and migration workstreams.

Timeline

Timeline 10 PhasesStart: Oct 2, 2026
Phase / Task
Oct 2026
Nov 2026
Dec 2026
Jan 2027
Feb 2027
W 1Oct 2
W 3Oct 16
W 5Oct 30
W 7Nov 13
W 9Nov 27
W 11Dec 11
W 13Dec 25
W 15Jan 8
W 17Jan 22
W 19Feb 5
Discovery, Governance and RequirementsOct 2 – Oct 15 · 2 wk · 0/4
Discovery, Governance and Requirements
Information Architecture and Content ModelOct 16 – Nov 5 · 3 wk · 0/6
Information Architecture and Content Model
UX and Visual DesignOct 30 – Nov 26 · 4 wk · 0/6
UX and Visual Design
Technical Architecture and Hosting SetupNov 6 – Nov 26 · 3 wk · 0/6
Technical Architecture and Hosting Setup
CMS Implementation and Core IntegrationsNov 20 – Dec 24 · 5 wk · 0/10
CMS Implementation and Core Integrations
PIM Product Catalogue IntegrationDec 11 – Jan 7 · 4 wk · 0/7
PIM Product Catalogue Integration
Careers, Content Migration and LocalizationDec 18 – Jan 14 · 4 wk · 0/7
Careers, Content Migration and Localization
Accessibility, SEO and Quality AssuranceJan 1 – Jan 21 · 3 wk · 0/7
Accessibility, SEO and Quality Assurance
User Acceptance, Training and Launch ReadinessJan 22 – Feb 4 · 2 wk · 0/4
User Acceptance, Training and Launch Readiness
Launch and StabilizationFeb 5 – Feb 18 · 2 wk · 0/4
Launch and Stabilization
PlannedIn progressCompletedBlockedMilestones

Budget

Budget: €230,500
CMS, PIM and Technical Integration · €80,550Discovery, Governance, Information Architecture and UX · €43,900Accessibility, SEO, Security and Quality Assurance · €42,100Content Migration, Careers and Localization · €41,650Hosting Setup, Training and Go-Live · €22,300
CMS, PIM and Technical Integration€80,550
ItemQtyUnit priceTotal
Solution Architect8 Person days€1,200€9,600
Senior CMS Developer28 Person days€900€25,200
Frontend Component Developer18 Person days€800€14,400
PIM Integration Engineer25 Person days€950€23,750
DevOps and Security Engineer8 Person days€950€7,600
Discovery, Governance, Information Architecture and UX€43,900
ItemQtyUnit priceTotal
Senior Project Manager14 Person days€900€12,600
Business Analyst / Requirements Consultant10 Person days€950€9,500
Information Architect / Content Modeler8 Person days€900€7,200
UX/UI Designer14 Person days€850€11,900
Accessibility UX Reviewer3 Person days€900€2,700
Accessibility, SEO, Security and Quality Assurance€42,100
ItemQtyUnit priceTotal
QA Lead14 Person days€850€11,900
Browser, Device and Regression Testers12 Person days€600€7,200
WCAG 2.1 AA Accessibility Specialist8 Person days€1,000€8,000
SEO Migration Consultant10 Person days€950€9,500
GDPR and Security Test Consultant5 Person days€1,100€5,500
Content Migration, Careers and Localization€41,650
ItemQtyUnit priceTotal
Content Migration Specialist15 Person days€750€11,250
German-English Localization Editor24 Person days€600€14,400
Product Data Quality Coordinator10 Person days€750€7,500
Careers and Recruitment Integration Specialist10 Person days€850€8,500
Hosting Setup, Training and Go-Live€22,300
ItemQtyUnit priceTotal
EU Hosting Environment Setup and Hardening1 Flat rate€6,500€6,500
Deployment, Monitoring and Backup Configuration1 Flat rate€4,500€4,500
CMS Editor and Administrator Training3 Person days€850€2,550
Launch and Cutover Support8 Person days€850€6,800
Operational Handover Documentation1 Flat rate€1,950€1,950

Risks

High

Product Data Quality and Regulatory Attribute Gaps

If more than 5% of sampled products have missing technical attributes, inconsistent units, incorrect classifications, outdated documents, or incomplete German-English data during Weeks 11–14, the catalogue may display inaccurate information and delay launch.

Countermeasure: Product Management and Product Data Owners will define mandatory attributes, units, validation rules, and approved regulatory claims by Week 5; the implementation partner will complete a representative data-quality audit and obtain product-owner sign-off by Week 14.
High

CMS and PIM Integration Failure

If the PIM API specification, ownership model, or synchronization rules are not approved by Week 8, or if two consecutive integration test cycles fail during Weeks 11–13, product pages, assets, filters, or availability information may not render reliably.

Countermeasure: IT, the implementation partner, and Product Data Owners will approve interface specifications, error handling, monitoring, and reconciliation procedures by Week 8, then complete end-to-end and failure-recovery testing before the Week 14 integration milestone.
High

SEO Visibility Loss During URL Migration

If the URL inventory and redirect map are incomplete, or redirect, canonical, sitemap, and indexation tests show less than 99% coverage by Week 16, the launch may cause ranking losses, broken links, and reduced organic traffic.

Countermeasure: The SEO and Analytics Owner will create and approve a page-level URL and redirect register by Week 12; the implementation partner will implement and crawl-test redirects, canonicals, robots rules, XML sitemaps, and structured data before the Week 18 go-live authorization.
High

WCAG 2.1 AA and Accessible Document Non-Compliance

If automated and manual testing identifies unresolved Level A or serious Level AA issues in navigation, forms, search, product filters, PDFs, careers workflows, or third-party components during Weeks 14–16, redesign and legal or reputational exposure may delay launch.

Countermeasure: The UX Lead and QA Lead will apply accessible design patterns from Week 5, test with keyboard navigation, screen readers, contrast tools, and representative assistive technologies by Week 16, and require documented remediation or risk acceptance before UAT.
High

GDPR, Consent and EU Hosting Misconfiguration

If data flows, processor agreements, sub-processors, retention rules, consent settings, or hosting access locations remain unapproved by Week 16, contact forms, careers applications, analytics, or cookies may process personal data unlawfully.

Countermeasure: The Data Protection Officer, Legal, IT, and the hosting provider will complete a processing inventory, DPIA screening, DPA/subprocessor review, consent test, retention design, and EU-region hosting validation by Week 16, with production access restricted and logged before launch.
High

Security, Backup and Operational Readiness Gaps

If penetration testing identifies unresolved high-severity vulnerabilities, or if backup restoration, monitoring, deployment, rollback, and incident-response rehearsals fail by Week 18, launch defects could cause downtime or loss of editorial and product data.

Countermeasure: IT, the hosting provider, and the implementation partner will complete vulnerability testing, patching, backup restoration, monitoring setup, access reviews, rollback rehearsal, and operational runbook approval before the Week 18 go-live decision.
Medium

Bilingual Content and Terminology Inconsistency

If priority German and English pages, product attributes, legal text, or careers content are not fully translated and reviewed by Week 15, users may receive contradictory technical, commercial, or employment information.

Countermeasure: Marketing, Product Data Owners, HR, and designated language representatives will approve a bilingual glossary and translation ownership model by Week 5; all priority content will receive independent language review and completeness sign-off by Week 15.
Medium

Careers and Recruitment Integration Dependency

If the careers feed, ATS interface, application links, consent wording, or tracking integration has not passed HR and technical testing by Week 13, vacancies may be missing, duplicated, outdated, or forced into a manual process at launch.

Countermeasure: HR and IT will confirm the ATS interface, data fields, update frequency, privacy notices, and fallback process by Week 8; the implementation partner will complete feed failure, accessibility, security, and end-to-end application tests by Week 15.
Medium

Stakeholder Approval and Content Ownership Delays

If product, sales, HR, legal, country, or language reviewers miss the agreed three-business-day review window during Weeks 12–17, conflicting feedback or unowned pages may prevent formal acceptance and compress launch testing.

Countermeasure: The Project Manager will publish a decision and approval matrix by Week 2, assign named owners for every priority page by Week 5, and escalate overdue or conflicting decisions to the Executive Sponsor within two business days.
Medium

Scope Growth and Budget or Timeline Compression

If new product templates, integrations, languages, content volumes, accessibility remediation, or stakeholder requests increase approved scope by more than 10% after Week 5, the 12% reserve may be consumed before QA and launch readiness.

Countermeasure: The Project Manager and Executive Sponsor will baseline scope, budget, and acceptance criteria in Week 2, apply formal change control from Week 3, review forecast and reserve consumption weekly, and defer or separately fund non-critical requests before Week 14.

Stakeholders

ES

Executive Sponsor / Managing Director

Owns business outcomes, budget, scope escalation, and final go-live approval

Involve: Phase 1
MA

Marketing and Corporate Communications

Owns corporate messaging, brand consistency, campaign priorities, and editorial governance

Involve: Phase 1
PM

Product Management and Product Data Owners

Define product taxonomy, catalogue requirements, technical attributes, and data quality standards

Involve: Phase 1
SA

Sales and Customer Service

Validate customer journeys, product discovery, enquiries, downloads, and regional requirements

Involve: Phase 2
HR

Human Resources and Recruiting

Owns careers content, vacancies, application journeys, and employer-brand requirements

Involve: Phase 2
IA

IT and Enterprise Architecture

Approves CMS integration, identity and access, environments, security, support model, and technical operations

Involve: Phase 1
DP

Data Protection, Legal and Compliance

Reviews GDPR, cookies, forms, tracking, hosting arrangements, legal notices, and accessibility obligations

Involve: Phase 1
SA

SEO and Analytics Owner

Defines migration rules, measurement requirements, redirects, search visibility controls, and reporting

Involve: Phase 1
CE

Content Editors and Country or Language Representatives

Produce, review, translate, and maintain German and English content

Involve: Phase 2
EC

External CMS/PIM Implementation Partner

Delivers architecture, development, integration, migration support, and technical remediation

Involve: Phase 1
EH

EU Hosting, Security and Operations Provider

Implements hosting, monitoring, backups, deployment, incident response, and operational handover

Involve: Phase 4

Compliance

Mandatory

Complete a GDPR processing inventory covering contact forms, analytics, cookies, careers applications, hosting, PIM/CMS integrations, recipients, retention periods, data-subject rights, and processor agreements; complete DPIA screening where required.

Data Protection Officer, Legal and IT Weeks 1–16; ongoing after launch
Mandatory

Implement ePrivacy-compliant consent management for non-essential cookies, analytics, advertising tags, and similar technologies, including prior consent where required, an equally prominent refusal option, consent records, and withdrawal functionality.

Legal, Data Protection Officer and SEO/Analytics Owner Weeks 8–16; ongoing monitoring
Mandatory

Protect applicant and employee-related data in the careers section through lawful-basis and privacy notices, role-based access, restricted data collection, retention and deletion rules, secure transmission, and approved ATS processors.

HR, Data Protection Officer and IT Weeks 7–16; ongoing
Mandatory

Meet the project’s WCAG 2.1 AA target and assess alignment with EN 301 549 and applicable European or national accessibility obligations, including accessible templates, forms, navigation, multimedia, PDFs, product documents, and third-party components.

UX Lead, QA Lead, Legal and Content Owners Weeks 3–18; ongoing content governance
Mandatory

Publish accurate German and English legal disclosures, including provider identification/imprint, privacy information, cookie information, contact details, and applicable terms or disclaimers for digital services.

Legal and Marketing Weeks 10–17; review on material change
Optional

Host production and backup environments in approved EU regions, document subprocessors and support access locations, enforce encryption, least-privilege access, logging, vulnerability management, backups, restoration testing, and incident-response procedures.

IT, Enterprise Architecture and Hosting Provider Weeks 6–18; ongoing operations
Optional

Apply internal security and operational standards, including OWASP-based application testing, browser and device compatibility testing, release approvals, accessibility and SEO evidence, analytics validation, monitoring, rollback procedures, and formal go-live sign-off.

QA Lead, IT, Implementation Partner and Project Manager Weeks 14–20; ongoing release management

Milestones

  1. Week 2

    Approved requirements baseline, governance model, scope, success criteria, and delivery plan

    Depends on: Discovery, governance, and stakeholder alignment
  2. Week 5

    Approved sitemap, content model, product taxonomy, bilingual content rules, search requirements, and URL principles

    Depends on: Requirements baseline and content governance
  3. Week 8

    Approved accessible design system, responsive templates, and validated user journeys for all priority content types

    Depends on: Information architecture and content model
  4. Week 8

    Approved technical architecture with operational EU environments, security controls, integration specifications, and compliance decisions

    Depends on: Architecture and hosting setup
  5. Week 12

    CMS-enabled corporate website foundation with tested templates, workflows, search, forms, consent management, and analytics instrumentation

    Depends on: Technical architecture and CMS implementation
  6. Week 14

    Validated PIM-to-website integration with approved product taxonomy, representative catalogue data, bilingual product content, and tested product journeys

    Depends on: CMS foundation and product data readiness
  7. Week 15

    Careers functionality operational and all priority German-English content migrated, reviewed, assigned to owners, and ready for formal QA

    Depends on: PIM integration and content localization
  8. Week 16

    Signed QA report showing resolved critical defects, WCAG remediation status, tested SEO migration controls, and approved security and compliance results

    Depends on: Content migration and implemented functionality
  9. Week 18

    Signed business acceptance, trained operational users, approved launch checklist, and formal go-live authorization

    Depends on: QA completion and launch readiness
  10. Week 20

    Website live in German and English with validated redirects, integrations, monitoring, operational handover, and stabilization sign-off

    Depends on: Go-live authorization and launch execution

How this plan was created

This plan was created by PathHub AI from a single description: “Relaunch the corporate website of an industrial supplier with 300 employees in German and English: new CMS, product catalogue from the PIM, careers section, accessibility to WCAG 2.1 AA, SEO migration of existing URLs and hosting in the EU.” — without company context. With your departments, approval processes and compliance requirements it becomes much more precise.

Obligations

Obligations with lead time: what many think of too late

These obligations are typically triggered by a website relaunch (example: Germany). PathHub AI schedules them with lead time, warns when the schedule is too tight and shows the rule with its criteria under “Rule & evidence”, which you tick off and back with evidence. Not legal advice.

Privacy policy, consent management for cookies/tracking (Sec. 25 TDDDG) and agreements with used services before go-live
Required 1–3 weeks before go-livestatutory
Rule & evidence

Why: Every website with analytics, maps, video or marketing services processes personal data.

Legal basis: Sec. 25 TDDDG: consent before setting non-essential cookies and trackers; GDPR Art. 13 information from the first visit.

Rule from the compliance library
Telecommunications Digital Services Data Protection Act (TDDDG, formerly TTDSG)
Criteria
  • Cookie consent banner for all non-essential cookies and trackers
  • Active opt-in without pre-ticked boxes
  • Rejecting as easy as accepting
  • Consent withdrawal available at any time

If breached: TDDDG fines up to €300,000. GDPR fines up to €20m or 4% apply in parallel.

Evidence: In PathHub you tick off the criteria and attach evidence to each item as a file, link or note. Everything exports as a PDF evidence report.
Check accessibility of shop and checkout and publish an accessibility statement (BFSG)
Important 4–8 weeks before go-livestatutory
Rule & evidence

Why: Accessibility has been mandatory for online shops serving consumers since June 2025.

Applies: if consumers can conclude contracts online (e.g. shop, booking); micro-enterprises with fewer than 10 employees and at most EUR 2m turnover or balance sheet are exempt for services

Legal basis: The BFSG has applied since 28 June 2025 to e-commerce services for consumers.

Rule from the compliance library
Accessibility Strengthening Act (BFSG)
Criteria
  • Accessibility of certain products and services (e.g. e-commerce, banking, e-books) since 28 June 2025
  • Compliance with accessibility requirements (perceivability, operability, understandability, robustness)
  • Provision of accessibility information for consumers
  • Micro-enterprise exemption for services (fewer than 10 employees and at most €2m turnover)

If breached: Fine up to €100,000 per violation. Sales ban until remediated.

Evidence: In PathHub you tick off the criteria and attach evidence to each item as a file, link or note. Everything exports as a PDF evidence report.
Implement mandatory information, withdrawal notice, price display and order button correctly
Important 1–2 weeks before go-livestatutory
Rule & evidence

Why: Distance-selling errors are a frequent reason for warning letters and extend withdrawal periods.

Applies: when selling to consumers

Rule from the compliance library
Distance Selling Law
Criteria
  • Pre-contractual information obligations for distance contracts (Art. 246a EGBGB)
  • Proper cancellation policy and provision of the model withdrawal form
  • 14-day right of withdrawal for consumers
  • Clearly designed ordering process with the "button solution" (order with obligation to pay)
  • Transparent information on total price, delivery/shipping costs and contract term

If breached: Warnings and injunctions by competitors/consumer associations. Fines up to €250,000.

Evidence: In PathHub you tick off the criteria and attach evidence to each item as a file, link or note. Everything exports as a PDF evidence report.
Register in the LUCID packaging register and license packaging with a scheme
Important 1–2 weeks before go-livestatutory
Rule & evidence

Why: Without registration, selling is prohibited.

Applies: if packaged goods are shipped to private end consumers

Legal basis: Packaging Act: registration in the LUCID register and system participation before first placing on the market.

Rule from the compliance library
Packaging Act
Criteria
  • Registration in the LUCID packaging register before placing on the market
  • System participation (licensing) of sales packaging subject to participation with a dual system
  • Identical volume reporting to LUCID and the dual system
  • Declaration of completeness when statutory volume thresholds are exceeded
  • Observance of take-back and deposit obligations (e.g. one-way deposit)

If breached: Sales and distribution ban for non-registration. Fines up to €200,000.

Evidence: In PathHub you tick off the criteria and attach evidence to each item as a file, link or note. Everything exports as a PDF evidence report.
All typical initiatives and their obligations: planning internal projects

Frequently asked questions

How long does a website relaunch take?
In the example plan, a website relaunch takes 20 weeks in 10 phases, of which 6 phases partly run in parallel. The actual duration depends on company size, starting point and available resources — with your company context PathHub adjusts the schedule accordingly.
What does a website relaunch cost?
The example plan estimates about €230,500, split into 24 budget line items with quantity and unit price. The largest items are CMS, PIM and Technical Integration, Discovery, Governance, Information Architecture and UX. This is an AI estimate as a starting point, not a quote.
What are the risks of a website relaunch?
The plan lists 10 risks with countermeasures. Rated highest: Product Data Quality and Regulatory Attribute Gaps; CMS and PIM Integration Failure; SEO Visibility Loss During URL Migration.
Who needs to be involved in a website relaunch?
Among others, the plan includes these people: Executive Sponsor / Managing Director, Marketing and Corporate Communications, Product Management and Product Data Owners, Sales and Customer Service, Human Resources and Recruiting, IT and Enterprise Architecture. For each role it states why and from when to involve them.
Can I adapt the plan to my company?
Yes. Open the plan in PathHub without signing up, adjust phases and tasks or describe your own initiative — with company context (departments, approval processes, works council, compliance requirements) every further plan gets more precise.