Project plan for an ERP implementation
An ERP implementation project plan structures requirements, process design, data migration, system integration, training, governance and go-live activities across a defined schedule and budget. This PathHub AI example covers a two-site machinery manufacturer in 10 phases, with 67 tasks over 28 weeks and an approximate budget of €577,600. It also assigns responsibilities, dependencies, risks, stakeholders and approval gates.
- 28 Weeks
- 10 Phases
- 67 Tasks
- Budget approx. €577,600
No sign-up · opens instantly
Your own project? The AI project plan generator builds a plan like this from a short description.
This is how the plan looks in PathHub. Pick a tab or open the plan live to tick off tasks and edit everything.






The plan in detail
Everything in the example plan to read through. In the live plan you can take it over and adapt it.
Phases and tasks
Phase 1: Project Mobilization and Governance
Establish the governance structure, decision rights, implementation method, and resources for the ERP replacement. This phase creates the control framework needed to deliver the nine-month go-live across both manufacturing sites.
- Important Approve the ERP project charter covering scope, objectives, two-site rollout, nine-month deadline, budget controls, and success criteriaExecutive Sponsor and Steering Committee · 3 days
- Appoint workstream leads, site representatives, key users, vendor consultants, and the internal project team for production, planning, materials, warehouse, finance, IT, and dataERP Project Manager · 3 days
- Establish the decision log, issue and risk register, change-control procedure, escalation path, meeting cadence, and reporting templatesERP Project Manager · 2 days
- Create the integrated 39-week delivery plan with workstream dependencies, employee release requirements, vendor commitments, site activities, and major approval gatesERP Project Manager and ERP Vendor and Implementation Partner · 4 days
Phase 2: Current-State Analysis and Requirements
Document how both sites currently manage production, materials, planning, warehousing, finance, reporting, and spreadsheet-based workarounds. The outcome is a validated requirements baseline that distinguishes common processes from site-specific needs.
- Important Map the current production processes from order release through routing, labor reporting, material issue, completion, rework, and production confirmation at both sitesProduction and Operations Lead · 5 days
- Important Document materials management, purchasing, replenishment, inventory control, supplier management, and spreadsheet-based stock tracking, including differences between the two sitesMaterials Management and Procurement Lead · 5 days
- Document production planning, capacity planning, scheduling, lead times, bottlenecks, planning parameters, and manual planning adjustmentsProduction Planning Lead · 4 days
- Analyse warehouse receiving, put-away, picking, staging, dispatch, stock transfers, cycle counts, labeling, and current barcode or manual identification practicesWarehouse and Logistics Lead · 4 days
- Define finance, accounting, management reporting, reconciliation, period-closing, tax, and legacy accounting interface requirementsFinance and Accounting Lead · 4 days
- Inventory current master data sources, spreadsheets, reports, traceability records, user roles, and system pain points, and validate requirements with key users and employee representatives where applicableIT and Integration Lead and Quality and Traceability Representative · 5 days
Phase 3: Solution Design and Fit-Gap Assessment
Define the future-state ERP processes and determine which requirements can be met by standard functionality, configuration, or controlled extensions. The phase prevents uncontrolled customization while ensuring that production, planning, warehouse, and financial needs are covered.
- Important Design the harmonized future-state process model for production, materials management, purchasing, planning, inventory, warehouse execution, and financial postings across both sitesERP Vendor and Implementation Partner and ERP Project Manager · 6 days
- Perform fit-gap workshops against the legacy production system, spreadsheets, and existing operational procedures, documenting standard solutions, configuration needs, extensions, and rejected requirementsERP Vendor and Implementation Partner · 5 days
- Define the production model, including item structures, bills of material, routings, work centres, operations, production versions, confirmations, scrap, rework, and traceabilityProduction and Operations Lead and Production Planning Lead · 5 days
- Define planning and replenishment principles covering demand inputs, MRP parameters, capacity constraints, safety stocks, lead times, lot sizes, and exception handlingProduction Planning Lead · 4 days
- Define the target warehouse and barcode process model, including locations, stock statuses, movement types, labels, scanner transactions, and site transfer rulesWarehouse and Logistics Lead · 4 days
- Define the target finance model for accounts, cost centres, inventory valuation, production variances, postings, interfaces, reconciliation, and management reportingFinance and Accounting Lead · 4 days
- Important Approve the fit-gap decisions, customization backlog, standardization principles, future-state process owners, and acceptance criteria for each workstreamExecutive Sponsor and Steering Committee · 3 days
Phase 4: Data and Integration Architecture
Establish the technical and business architecture for migrating legacy and spreadsheet data and connecting the ERP with accounting and other required systems. Clear ownership and reconciliation rules are defined before configuration and migration work begin.
- Important Define the accounting interface architecture, transaction scope, field mappings, posting rules, error handling, security, monitoring, and reconciliation requirementsIT and Integration Lead and Finance and Accounting Lead · 5 days
- Catalogue migration objects for items, customers, suppliers, bills of material, routings, work centres, inventory, open orders, prices, planning parameters, users, and opening balancesIT and Integration Lead and ERP Vendor and Implementation Partner · 4 days
- Assign data owners, quality rules, approval responsibilities, retention requirements, and source systems for each master-data and transactional-data objectERP Project Manager · 3 days
- Define the migration architecture, extraction templates, transformation rules, validation checks, load sequence, reconciliation approach, and rollback requirementsERP Vendor and Implementation Partner · 4 days
- Design the technical environment, user roles, authentication, network requirements, backups, audit logging, interface monitoring, and support escalation modelIT and Integration Lead · 4 days
Phase 5: ERP Configuration and Process Build
Configure and build the core ERP solution based on the approved future-state design. The work covers production, materials, purchasing, planning, inventory, finance-related processes, workflow, reporting, and user security.
- Important Configure production master data structures, bills of material, routings, work centres, production orders, operation confirmations, scrap, rework, and traceability transactionsERP Vendor and Implementation Partner and Production and Operations Lead · 8 days
- Important Configure planning, MRP, capacity requirements, demand management, safety stocks, lead times, lot sizing, exception messages, and planning calendarsERP Vendor and Implementation Partner and Production Planning Lead · 7 days
- Configure item master, supplier master, purchasing, purchase requisitions, purchase orders, goods receipts, invoice matching, replenishment, and approval workflowsMaterials Management and Procurement Lead and ERP Vendor and Implementation Partner · 7 days
- Configure inventory management, stock statuses, lot or serial tracking where required, transfers between sites, adjustments, cycle counts, and inventory valuation inputsERP Vendor and Implementation Partner and Warehouse and Logistics Lead · 6 days
- Configure sales or production demand inputs, customer and supplier records, order status tracking, and operational transaction controls required by the manufacturerERP Vendor and Implementation Partner · 5 days
- Build the accounting interface, financial posting rules, cost-centre mappings, inventory and production variance postings, interface error handling, and reconciliation reportsIT and Integration Lead and Finance and Accounting Lead · 8 days
- Configure approval workflows for purchasing, master-data changes, inventory adjustments, production exceptions, and financial controlsERP Vendor and Implementation Partner · 4 days
- Configure management reports and operational dashboards for production output, schedule adherence, inventory, shortages, purchasing, warehouse accuracy, and financial reconciliationFinance and Accounting Lead and ERP Vendor and Implementation Partner · 5 days
- Set up role-based security for shop-floor, planning, purchasing, warehouse, finance, management, site, and support users across the 180-employee populationIT and Integration Lead · 4 days
- Develop and document approved ERP extensions, reports, forms, and workflow changes that cannot be delivered through standard configurationERP Vendor and Implementation Partner · 6 days
- Important Execute configuration unit tests for each workstream, record evidence, resolve priority defects, and prepare the integrated test environmentERP Project Manager and ERP Vendor and Implementation Partner · 5 days
Phase 6: Barcode Warehouse Implementation
Implement the barcode-enabled warehouse processes at both sites, including physical locations, scanners, printers, labels, stock transactions, and user procedures. The objective is reliable real-time inventory visibility and controlled material movement.
- Important Finalize warehouse layouts, location numbering, staging areas, receiving points, dispatch zones, and site-transfer procedures for both locationsWarehouse and Logistics Lead and Site Managers for Both Locations · 4 days
- Select, procure, configure, and register handheld scanners, label printers, accessories, and required warehouse hardware for both sitesIT and Integration Lead · 5 days
- Configure barcode formats, item and location labels, packaging labels, goods-receipt labels, production issue labels, and dispatch documentationERP Vendor and Implementation Partner and Warehouse and Logistics Lead · 5 days
- Configure and test scanner transactions for receiving, put-away, picking, production staging, material issue, production receipt, transfers, cycle counts, and dispatchERP Vendor and Implementation Partner · 7 days
- Validate wireless coverage, device connectivity, printer connectivity, charging arrangements, user authentication, and offline or recovery procedures in operational warehouse areasIT and Integration Lead · 4 days
- Important Conduct physical pilot runs with representative materials, pallets, production orders, site transfers, and dispatches at both sites and correct usability or transaction defectsWarehouse and Logistics Lead and Quality and Traceability Representative · 5 days
- Create warehouse work instructions covering scanning sequence, exception handling, damaged labels, stock discrepancies, device care, and escalation proceduresWarehouse and Logistics Lead · 4 days
Phase 7: Data Cleansing and Migration Rehearsals
Clean, standardize, validate, and rehearse the migration of data from the legacy production system and spreadsheets. Repeated migration cycles establish confidence in master data, open transactions, inventory, production structures, and opening financial balances.
- Important Extract and profile item masters, bills of material, routings, work centres, suppliers, customers, inventory, open orders, prices, planning parameters, and financial opening dataIT and Integration Lead and ERP Vendor and Implementation Partner · 5 days
- Cleanse and standardize duplicate items, units of measure, supplier records, descriptions, locations, bills of material, routings, lead times, and planning parametersMaterials Management and Procurement Lead and Production Planning Lead · 7 days
- Validate production and quality data, including revision status, traceability attributes, approved materials, scrap factors, rework rules, and required historical referencesProduction and Operations Lead and Quality and Traceability Representative · 5 days
- Reconcile inventory quantities, locations, valuation, open purchase orders, production orders, reservations, and inter-site balances against approved legacy reportsWarehouse and Logistics Lead and Finance and Accounting Lead · 5 days
- Important Execute Migration Rehearsal 1 using the defined extraction, transformation, loading, validation, and exception-resolution proceduresERP Vendor and Implementation Partner and IT and Integration Lead · 5 days
- Important Execute Migration Rehearsal 2 with corrected data and production-like volumes, document reconciliation results, and confirm the final migration runbook and rollback stepsERP Project Manager and ERP Vendor and Implementation Partner · 5 days
Phase 8: End-to-End Testing and Business Readiness
Validate integrated business scenarios across both sites, from demand and purchasing through production, warehousing, accounting, and management reporting. Business users confirm that the ERP can support daily operations before training and cutover approval.
- Important Execute end-to-end scenario tests covering demand, MRP, purchasing, receiving, warehouse movements, production issue, production completion, dispatch, and financial postingERP Project Manager and ERP Vendor and Implementation Partner · 7 days
- Test representative machinery-manufacturing scenarios, including multi-level bills of material, long-lead materials, capacity constraints, rework, scrap, substitutions, and partial production completionsProduction and Operations Lead and Production Planning Lead · 5 days
- Test both-site processes for inter-site transfers, shared materials, local purchasing, location-specific inventory, common master data, and site reportingSite Managers for Both Locations and Materials Management and Procurement Lead · 4 days
- Important Reconcile accounting interface results for goods receipts, inventory movements, production variances, purchases, invoices, adjustments, cost centres, and opening balancesFinance and Accounting Lead and IT and Integration Lead · 5 days
- Test barcode warehouse scenarios under realistic operating conditions, including receiving, picking, production staging, cycle counting, damaged labels, stock discrepancies, and dispatchWarehouse and Logistics Lead · 5 days
- Test user roles, approvals, segregation of duties, audit trails, error messages, interface monitoring, backups, recovery procedures, and report accessIT and Integration Lead · 4 days
- Conduct performance and volume testing using representative master-data and transaction volumes from both sitesIT and Integration Lead and ERP Vendor and Implementation Partner · 3 days
- Triage defects by severity, coordinate corrections, execute regression tests, and maintain a documented decision on deferred issues and workaroundsERP Project Manager and ERP Vendor and Implementation Partner · 8 days
- Important Conduct business user acceptance testing with nominated key users and obtain formal acceptance from production, planning, materials, warehouse, finance, and both site managersERP Project Manager · 5 days
Phase 9: Training, Cutover Preparation, and Go-Live Readiness
Prepare employees for the new ERP processes and complete all operational, technical, data, and support preparations for go-live. Readiness is assessed separately for both sites and for every critical business function.
- Important Deliver role-based training for production, planning, purchasing, materials, warehouse, finance, management, IT support, and site leadership usersERP Vendor and Implementation Partner and Functional Workstream Leads · 8 days
- Establish super users and floor-support coverage, and conduct train-the-trainer sessions using realistic machinery-manufacturing transactions and barcode workflowsERP Project Manager and Department Leads · 4 days
- Finalize work instructions, quick-reference guides, process maps, exception procedures, barcode instructions, and local site supplementsFunctional Workstream Leads · 6 days
- Important Prepare and approve the detailed cutover plan covering transaction freeze, final extraction, stock count, data load, interface activation, user provisioning, hardware deployment, validation, communications, and rollback triggersERP Project Manager and IT and Integration Lead · 6 days
- Complete final master-data validation, opening-balance preparation, stock-count instructions, open-order treatment, and cutover data sign-offFinance and Accounting Lead and Warehouse and Logistics Lead · 5 days
- Confirm production support, vendor escalation, help-desk routing, monitoring, incident severity definitions, on-call coverage, and daily hypercare reportingIT and Integration Lead · 4 days
- Important Conduct the final go-live readiness review covering training completion, test status, data quality, hardware, interfaces, site preparedness, support coverage, and business continuityExecutive Sponsor and Steering Committee · 3 days
Phase 10: Go-Live and Hypercare
Execute the cutover from the legacy production system and spreadsheets to the ERP, stabilize daily operations, and transition the solution to normal support. Hypercare focuses on production continuity, inventory accuracy, accounting integrity, and rapid issue resolution.
- Important Execute the approved cutover, including legacy transaction freeze, final data extraction and loading, opening balances, user activation, interface enablement, barcode deployment, and go-live validation at both sitesERP Project Manager and IT and Integration Lead · 3 days
- Provide on-site and remote hypercare for production, planning, purchasing, warehouse, barcode, finance, and management-reporting processes during the first operating daysERP Vendor and Implementation Partner and Functional Workstream Leads · 7 days
- Monitor production orders, material availability, warehouse movements, stock accuracy, interface queues, accounting postings, and critical management reports through daily operational reviewsERP Project Manager and Site Managers for Both Locations · 10 days
- Resolve priority incidents, apply approved corrections or workarounds, update knowledge articles, and track outstanding defects against agreed service levelsIT and Integration Lead and ERP Vendor and Implementation Partner · 10 days
- Complete the first financial and inventory reconciliation, assess operational performance, transfer support ownership, and conduct a post-go-live review against the approved success criteriaFinance and Accounting Lead and ERP Project Manager · 5 days
Budget
| Item | Quantity | Unit price | Total |
|---|---|---|---|
| Internal Personnel and Operational Backfill | |||
| Internal ERP Project Coordinator | 20 Person days | €850 | €17,000 |
| Business Workstream Leads and Key Users | 40 Person days | €250 | €10,000 |
| Operational Backfill for Workshops and Testing | 20 Person days | €150 | €3,000 |
| External ERP Consulting and Process Design | |||
| ERP Implementation Project Manager | 35 Person days | €1,000 | €35,000 |
| Manufacturing and Production Planning Consultant | 45 Person days | €1,200 | €54,000 |
| Materials Management and Warehouse Consultant | 30 Person days | €1,100 | €33,000 |
| Finance and Accounting Interface Consultant | 25 Person days | €1,200 | €30,000 |
| ERP Technical Configuration and Development Consultant | 25 Person days | €900 | €22,500 |
| ERP Software and System Integration | |||
| Manufacturing ERP Licenses and Initial User Setup | 1 Flat rate | €90,000 | €90,000 |
| Accounting Connector and Integration Middleware | 1 Flat rate | €15,000 | €15,000 |
| Accounting Interface Developer | 25 Person days | €1,200 | €30,000 |
| Barcode Warehouse Hardware and Infrastructure | |||
| Industrial Barcode Handheld Scanners | 12 Person days | €1,800 | €21,600 |
| Industrial Barcode Label Printers | 4 Person days | €2,500 | €10,000 |
| Warehouse Wireless Network and Site Installation | 1 Flat rate | €12,000 | €12,000 |
| Mobile Warehouse Software Licenses | 2 Person days | €4,000 | €8,000 |
| Initial Barcode Labels and Consumables | 1 Flat rate | €6,000 | €6,000 |
| Data Migration, Testing, Training, and Deployment | |||
| Data Migration Lead | 35 Person days | €1,100 | €38,500 |
| Data Cleansing and Master Data Analyst | 45 Person days | €700 | €31,500 |
| Migration Templates and Data Conversion Tooling | 1 Flat rate | €12,000 | €12,000 |
| Test Manager and Integration Test Coordination | 25 Person days | €1,000 | €25,000 |
| Test Automation and Defect Management Support | 15 Person days | €800 | €12,000 |
| Training and Change Management Lead | 25 Person days | €900 | €22,500 |
| Training Materials, Work Instructions, and E-Learning Content | 1 Flat rate | €12,000 | €12,000 |
| Cutover and Hypercare Support Consultants | 18 Person days | €1,100 | €19,800 |
| Cross-Site Travel and Workshop Expenses | 1 Flat rate | €7,200 | €7,200 |
| Sum of items | €577,600 | ||
Risks
Scope Expansion and Uncontrolled Customization
High impactIf requirements are added after the signed-off catalogue in Week 6, or more than a small number of material gaps require custom development after Week 9, the configuration, testing, budget, and nine-month go-live date may become unachievable.
Countermeasure: The ERP Project Manager and Steering Committee will approve a scope baseline, fit-gap decision log, and formal change-control process by the end of Week 2. The ERP Vendor and process leads will classify each gap as standard configuration, controlled extension, workaround, or deferred requirement by Week 9; the Finance Lead will track contingency consumption monthly.
Inadequate Legacy and Spreadsheet Data Quality
High impactIf data owners have not profiled and cleansed inventory, bills of material, routings, suppliers, customers, locations, and open transactions by Week 14, migration errors may cause incorrect stock, purchasing, production, or customer records at go-live.
Countermeasure: The IT and Integration Lead will assign an accountable owner to every migration object by Week 9. Functional leads will define validation rules by Week 10, data owners will complete cleansing before each rehearsal, and IT will require two successful migration rehearsals with reconciliation evidence by Week 17.
Unreliable Production Planning and Manufacturing Master Data
High impactIf bills of material, routings, work centres, capacity calendars, lead times, yield factors, or planning parameters fail agreed accuracy tests during Weeks 15-17, MRP and production schedules may generate shortages, excess inventory, unrealistic dates, or shop-floor disruption.
Countermeasure: The Production Planning Lead and Production and Operations Lead will establish master-data quality thresholds by Week 10 and validate representative products from both sites by Week 15. The planning team will run constrained planning scenarios during end-to-end testing, and no-go-live approval will be granted unless critical planning defects are closed or explicitly accepted by the Steering Committee by Week 21.
Accounting Interface and Financial Reconciliation Failure
High impactIf account mappings, tax treatment, inventory valuation, cost flows, or interface error handling are not approved by Week 15, or if financial totals do not reconcile during the Week 17 rehearsal, postings, month-end close, tax reporting, and audit evidence may be incorrect.
Countermeasure: The Finance and Accounting Lead and IT and Integration Lead will approve the posting design and reconciliation rules by Week 12. They will test purchases, receipts, production issues, inventory adjustments, shipments, invoices, payments, and opening balances by Week 20, with zero unexplained material differences required before the Week 25 go-live decision.
Barcode Warehouse and Network Implementation Failure
High impactIf scanner connectivity, printer configuration, label readability, location data, or warehouse transaction procedures fail under realistic operating conditions during Weeks 15-17, stock accuracy, picking, receiving, production issuing, and dispatch may be disrupted at one or both sites.
Countermeasure: The Warehouse and Logistics Lead and IT Lead will complete a physical site survey and coverage test by Week 13. They will pilot receiving, put-away, picking, transfers, cycle counts, production consumption, and dispatch at both sites by Week 16, maintain spare devices and printed-label fallback procedures, and require successful operational acceptance before Week 21.
Loss of Product Traceability or Quality Records
High impactIf serial numbers, batch numbers, material certificates, inspection results, nonconformances, or links between purchased material and manufactured product are not defined and tested by Week 20, the business may be unable to demonstrate product history or respond effectively to quality issues and customer inquiries.
Countermeasure: The Quality and Traceability Representative will define mandatory traceability fields and retention rules by Week 9. Production, warehouse, and quality leads will test forward and backward traceability scenarios during end-to-end testing, and the Quality Representative will sign off the traceability evidence before the Week 25 go-live decision.
Unresolved Differences Between the Two Sites
Medium impactIf site-specific differences in inventory units, warehouse locations, production procedures, approval rules, or planning calendars remain unresolved after Week 9, the ERP may require inconsistent configurations, duplicate master data, or manual workarounds.
Countermeasure: The two Site Managers and functional leads will maintain a site-difference register from Week 3 and decide by Week 9 which processes will be harmonized, locally configured, or formally exempted. The ERP Project Manager will require both sites to approve one common process baseline and exception list before configuration is finalized in Week 15.
Insufficient Key-User Availability
High impactIf production, warehouse, planning, procurement, finance, or quality key users cannot provide the planned workshop, validation, and testing time during Weeks 3-21, decisions and defect resolution may be delayed and the solution may be accepted without adequate operational review.
Countermeasure: Site Managers and department heads will reserve named key-user capacity and operational backfill by Week 2. The ERP Project Manager will monitor attendance and decision turnaround weekly; any key-user availability below the approved plan for two consecutive weeks will be escalated to the Steering Committee for immediate backfill or scope adjustment.
Training and User Adoption Gaps
High impactIf fewer than 95% of critical users complete role-based training and practical assessment by the end of Week 25, employees may continue using spreadsheets, bypass barcode transactions, or enter incomplete ERP data after go-live.
Countermeasure: The ERP Project Manager, department leads, and vendor will create role-based training and work instructions by Week 22. Super-users will conduct practical exercises at both sites in Weeks 23-25, track completion and competency, and provide floor support during the first three weeks after go-live.
Vendor Capacity, Budget, and Schedule Pressure
High impactIf vendor deliverables, interface development, or critical defect fixes slip beyond their baseline dates—particularly configuration beyond Week 15 or critical testing defects beyond Week 21—the remaining schedule and the EUR 650,000 budget reserve may be insufficient for recovery.
Countermeasure: The ERP Project Manager will baseline vendor deliverables, acceptance criteria, dependencies, and resource commitments by Week 2. The Steering Committee will review schedule, budget, and reserve consumption every two weeks; the vendor will provide recovery plans within five business days of any critical slippage, with deferred scope or additional resources approved by Week 21 where necessary.
Go-Live Disruption and Inadequate Recovery Planning
High impactIf the cutover rehearsal does not prove opening balances, inventory status, open orders, user access, interfaces, and rollback steps by Week 24, production, purchasing, warehousing, dispatch, or financial close may be interrupted during Weeks 26-28.
Countermeasure: The ERP Project Manager, IT Lead, Finance Lead, and site leads will complete and approve a detailed cutover runbook, support roster, rollback criteria, and business-continuity procedures by Week 25. The Steering Committee will use formally agreed go/no-go criteria, and the project team will provide intensified vendor and super-user hypercare through Week 28.
Stakeholders
Executive Sponsor and Steering Committee
Approves scope, budget, major design decisions, and escalations
Involve: Phase 1
ERP Project Manager
Coordinates workstreams, schedule, risks, vendor activities, and decisions
Involve: Phase 1
IT and Integration Lead
Owns infrastructure, security, interfaces, technical testing, and support readiness
Involve: Phase 1
Site Managers for Both Locations
Resolve site-specific conflicts, provide operational resources, and approve local readiness
Involve: Phase 1
ERP Vendor and Implementation Partner
Provides product expertise, configuration, development, migration support, and defect resolution
Involve: Phase 1
Production and Operations Lead
Defines production execution requirements, shop-floor processes, and operational acceptance criteria
Involve: Phase 2
Production Planning Lead
Owns planning logic, scheduling parameters, capacity requirements, and planning validation
Involve: Phase 2
Materials Management and Procurement Lead
Defines purchasing, replenishment, inventory, supplier, and material master processes
Involve: Phase 2
Warehouse and Logistics Lead
Owns warehouse layout, barcode transactions, scanner usage, stock movements, and inventory accuracy
Involve: Phase 2
Finance and Accounting Lead
Defines financial postings, accounting controls, reporting, reconciliation, and interface acceptance
Involve: Phase 2
Quality and Traceability Representative
Ensures production records, material traceability, quality-related data, and audit requirements are represented
Involve: Phase 2
Employee Representatives or Works Council, if applicable
Reviews changes to employee workflows, monitoring, training, and working practices
Involve: Phase 2
Obligations and compliance
| Requirement | Owner | Timing | Type |
|---|---|---|---|
| Configure statutory accounting, tax, audit-trail, record-retention, financial-approval, and segregation-of-duties controls applicable to the company’s jurisdiction | Finance and Accounting Lead, IT and Integration Lead | Weeks 4-25, with ongoing operation | Mandatory |
| Consult employee representatives or a works council, where applicable, regarding workflow changes, user monitoring, personal data processing, training, and changes to working practices before implementation | HR, ERP Project Manager, Employee Representatives or Works Council | Weeks 2-22 | Mandatory |
| Align process ownership, document control, master-data governance, nonconformance handling, and audit evidence with the company’s ISO 9001 or equivalent quality-management system where maintained or contractually required | Quality and Traceability Representative, Process Owners | Weeks 3-25, then ongoing | Important |
| Implement role-based access, privileged-account control, segregation of duties, secure interfaces, backup and restore testing, change control, incident response, and business-continuity measures in line with internal IT security policy | IT and Integration Lead, ERP Vendor, Internal Security Owner | Weeks 1-28, then ongoing | Important |
| Update the record of processing activities and check whether a data protection impact assessment is needed (GDPR Art. 30, 35) | Data protection officer | 2–4 weeks before go-live (guide value) | Mandatory |
| Sign a data processing agreement with the provider (GDPR Art. 28) | Procurement / data protection | 2–6 weeks before go-live (statutory precondition) | Mandatory |
Milestones
| Week | Milestone | Prerequisite |
|---|---|---|
| 2 | Approved project charter, staffed workstreams, governance framework, and baseline implementation schedule | Project mobilization and governance |
| 6 | Signed-off current-state process maps, requirements catalogue, site-difference register, and master-data source inventory | Current-state analysis and requirements |
| 9 | Approved future-state design, fit-gap catalogue, customization decisions, and process acceptance criteria | Solution design and fit-gap assessment |
| 9 | Approved integration specification, migration object catalogue, data ownership matrix, and technical architecture | Data and integration architecture |
| 15 | Core ERP configuration completed, approved extensions delivered, security roles assigned, and unit-test exit criteria met | ERP configuration and process build |
| 16 | Barcode hardware installed, warehouse transactions validated at both sites, and approved warehouse operating procedures completed | Barcode warehouse implementation |
| 17 | Approved migration datasets, two completed migration rehearsals, reconciliation evidence, and signed migration runbook | Data cleansing and migration rehearsals |
| 21 | Critical end-to-end defects closed or formally accepted, business acceptance completed, and test exit approval granted | End-to-end testing and business readiness |
| 25 | Approved cutover plan, completed critical-user training, signed site readiness checklists, and formal go-live decision | Training, cutover preparation, and go-live readiness |
| 28 | ERP live at both sites, critical operations stabilized, first reconciliations completed, and ownership transferred to the support organization | Go-live and hypercare |
How this plan was created
This plan was created by PathHub AI from a single description: “Introduce a new ERP system in a machinery manufacturer with 180 employees at two sites: replace spreadsheets and a legacy production system, materials management, production planning, barcode warehouse, accounting interface, data migration and training. Go-live in nine months.” Without company context. With your departments, approval processes and compliance requirements it becomes much more precise.
Related documents
The requirements specification usually comes before the project plan. Here is the matching example with Word download.
Obligations with lead time: what many think of too late
These obligations are typically triggered by an ERP implementation (example: Germany). PathHub AI schedules them with lead time, warns when the schedule is too tight and shows the rule with its criteria under “Rule & evidence”, which you tick off and back with evidence. Not legal advice.
Rule & evidence
Why: The new system processes personal data of customers or employees.
- Legal basis for every processing of personal data (consent, contract, legal obligation, legitimate interest)
- Complete record of processing activities (Art. 30) for all processes
- Data Processing Agreements (DPA) with all sub-processors
- Data Protection Impact Assessment (DPIA) for high-risk processing
- Technical and organisational measures (TOM) documented
If breached: Fines up to €20 million or 4% of global annual revenue, whichever is higher. Plus civil damages claims by affected individuals.
Rule & evidence
Why: The provider processes personal data on your behalf (cloud, maintenance, support).
Legal basis: GDPR Art. 28: the contract must be in place before processing starts, including tests with real data or data migration.
- Data Processing Agreement (DPA) with cloud provider
- SLA with availability, RPO, RTO
- Exit and portability clause
- Data localisation and transfer mechanism (SCC / adequacy)
If breached: Civil claims for data loss; recourse depends on contract. GDPR fines for non-compliance.
Rule & evidence
Why: Almost any software logs user actions and is therefore suitable for monitoring performance or behaviour.
Applies: only if a works council exists
Legal basis: Sec. 87(1) No. 6 Works Constitution Act: co-determination for technical systems suitable for monitoring behaviour or performance; suitability is enough. Without agreement the system must not be introduced.
- Enable works council election from 5 eligible employees upward
- Co-determination on working time, monitoring systems, IT rollouts (§87)
- Hearing before every dismissal (§102): written with reasons
- Balance-of-interests and social plan on operational changes (§111)
If breached: Dismissals without works council hearing are void. Administrative fines up to €10,000 per violation. Criminal liability (§119) for obstructing the works council up to 1 year imprisonment.
Rule & evidence
Why: Tax-relevant data must be retained completely, unalterably and auditably, also after the system change.
Applies: if the system processes accounting or tax-relevant data (ERP, invoices, POS)
- Process documentation for all tax-relevant systems and procedures
- Complete and unalterable records, changes are logged
- Retention of tax-relevant documents for the statutory period (generally 8 or 10 years)
- Data access for tax audits possible (Sec. 147(6) German Fiscal Code)
- Receipt of structured e-invoices (XRechnung, ZUGFeRD) since 1 Jan 2025
- Issuing e-invoices to domestic businesses: from 2027 for prior-year turnover above EUR 800,000, from 2028 generally for all (exceptions incl. small-amount invoices, small businesses)
If breached: Formal defects can lead to the bookkeeping being rejected and the tax base being estimated (Sec. 162 German Fiscal Code); refusing data access can trigger a delay penalty (Sec. 146(2c)).