Project plan for an office move

An office move touches almost every department: IT, facilities, purchasing, HR and the works council. This plan shows how to move 60 employees to a new building without disrupting operations.

No sign-up · opens instantly · 11 Weeks · 6 Phases · 30 Tasks · Budget approx. €98,000

This is how the plan looks in PathHub — click through the tabs or tick off tasks.

app.pathhub.ai/try?example=move-enOpen live
Example plan

Office Relocation and Business Continuity Project

This project will relocate a 60-employee office to a new building by the end of Q2 while maintaining business continuity. The work includes site readiness checks, workplace design, procurement, IT and telecom preparation, employee communications, packing, and a controlled move execution. The plan assumes the new building is already secured and only limited fit-out is required. Success depends on careful sequencing, supplier coordination, and a low-disruption cutover.

Total Progress0%
11Weeks
0/6Phases
0/30Tasks
€98,000Budget
AI Recommendations KIAI Chat KIAI Tools KI

Phases

1

Phase 1: Initiation and Requirements Definition

Pending · 1W · 0/3
Project Manager or Office Manager
0

Establish the relocation mandate, decision rights, requirements, budget baseline, and operational constraints for moving 60 employees by the end of Q2. This creates the governance and acceptance criteria needed to protect business continuity.

Timeline

Timeline 6 PhasesStart: Oct 1, 2026
Phase / Task
Oct 2026
Nov 2026
Dec 2026
W 1Oct 1
W 2Oct 8
W 3Oct 15
W 4Oct 22
W 5Oct 29
W 6Nov 5
W 7Nov 12
W 8Nov 19
W 9Nov 26
W 10Dec 3
W 11Dec 10
Initiation and Requirements DefinitionOct 1 – Oct 7 · 1 wk · 0/3
Initiation and Requirements Definition
New-Site Due Diligence and Readiness PlanningOct 8 – Oct 21 · 2 wk · 0/5
New-Site Due Diligence and Readiness Planning
Workplace Design, Procurement, and Move PlanningOct 22 – Nov 11 · 3 wk · 0/6
Workplace Design, Procurement, and Move Planning
IT, Telecom, and Facilities PreparationNov 12 – Dec 2 · 3 wk · 0/7
IT, Telecom, and Facilities Preparation
Communications, Packing, and Cutover RehearsalNov 26 – Dec 9 · 2 wk · 0/5
Communications, Packing, and Cutover Rehearsal
Move Execution and StabilizationDec 10 – Dec 16 · 1 wk · 0/4
Move Execution and Stabilization
PlannedIn progressCompletedBlockedMilestones

Budget

Budget: €98,000
IT, Network, Telephony & Access Control · €22,500Premises Preparation & Minor Fit-Out · €18,000Professional Moving, Packing & Transport · €17,500Internal Personnel & Governance · €15,500Security, Cleaning, Utilities & Employee Operations · €13,500Furniture & Workplace Equipment · €11,000
IT, Network, Telephony & Access Control€22,500
ItemQtyUnit priceTotal
Structured Network Installation and Testing1 Flat rate€9,000€9,000
Internet Circuit and Telecom Activation1 Flat rate€4,500€4,500
IT Workstation, Telephony and Access-Control Cutover Engineer9 Person days€1,000€9,000
Premises Preparation & Minor Fit-Out€18,000
ItemQtyUnit priceTotal
Site Readiness and Health & Safety Consultant3 Person days€1,000€3,000
Electrical, cabling, minor partitions, repairs and signage1 Flat rate€15,000€15,000
Professional Moving, Packing & Transport€17,500
ItemQtyUnit priceTotal
Professional Moving Crew20 Person days€450€9,000
Packing Materials, Asset Labels and Secure Packing Supplies1 Flat rate€3,000€3,000
Transport, Furniture Handling, Transit Insurance and Disposal1 Flat rate€5,500€5,500
Internal Personnel & Governance€15,500
ItemQtyUnit priceTotal
Project Manager / Office Manager, including supplier and move coordination15 Person days€900€13,500
Finance and Procurement Coordinator4 Person days€500€2,000
Security, Cleaning, Utilities & Employee Operations€13,500
ItemQtyUnit priceTotal
Final Cleaning, Waste Removal, Security Administration and Overlapping Utilities1 Flat rate€6,500€6,500
Employee Communications, Briefings and Move Instructions8 Person days€250€2,000
Temporary Workspace, Move-Day Supplies and Contingency Operations1 Flat rate€5,000€5,000
Furniture & Workplace Equipment€11,000
ItemQtyUnit priceTotal
Additional Desks and Office Chairs10 Person days€700€7,000
Storage, Meeting-Room and Ergonomic Equipment8 Person days€500€4,000

Risks

High

New-Building Readiness and Approval Delay

If landlord works, cabling, utilities, access permissions, fire-safety documentation, or occupancy approvals are not complete and accepted by the end of Week 8, the move window may be compressed or the building may be unsuitable for occupation by the end of Q2.

Countermeasure: The Facilities or Workplace Lead will complete site due diligence by Week 3, agree a remediation plan with the landlord by Week 4, track evidence of completion weekly, and conduct a formal building-readiness go/no-go review by Week 9. The Project Manager will maintain temporary workspace or remote-working capacity as a contingency.
High

IT, Telecom, and Access-Control Cutover Failure

If network connectivity, Wi-Fi, VPN, telephony, access control, workstations, or essential business applications fail integrated testing by Week 9, employees may be unable to work effectively on the first business day at the new site.

Countermeasure: The IT and Telecommunications Lead will complete installation and component testing by Week 8, perform integrated acceptance testing by Week 9, and conduct a cutover rehearsal in Week 10. IT will prepare verified backups, temporary connectivity, call-forwarding, remote-working support, and a documented rollback and incident-response procedure before the move.
High

Loss, Damage, or Unauthorized Disclosure of Personal and Business Data

If laptops, documents, storage media, credentials, or access badges are not inventoried, secured, and reconciled before transport in Week 10, equipment could be lost or damaged and personal or confidential information could be exposed during packing or the move.

Countermeasure: The IT Lead, HR, and the data-protection or information-security owner will complete an asset and data inventory by Week 9, apply tamper-evident labels and sealed containers, restrict handling to authorized movers, maintain chain-of-custody records, and reconcile all assets by the end of Week 11. Unneeded records and equipment will be securely destroyed through approved providers.
Medium

Moving Supplier or Loading-Window Failure

If the mover, lift access, loading bay, building access permissions, insurance, or transport route are not confirmed by Week 6, the move may be delayed, incur additional charges, or result in damage to furniture and equipment.

Countermeasure: Procurement and the Project Manager will contract the primary mover and confirm insurance, access arrangements, staffing, vehicle capacity, and loading windows by Week 6. The Facilities Lead will complete a route and loading survey by Week 7, while the Project Manager will retain a backup supplier or alternative move window before Week 9.
Medium

Workplace Health, Safety, Accessibility, and Employee Readiness Gaps

If the workplace risk assessment, emergency arrangements, accessibility checks, ergonomic setup, employee instructions, or evacuation roles are incomplete by Week 9, the move could create safety incidents, non-compliance, reduced productivity, or employee resistance.

Countermeasure: The Facilities Lead and applicable health-and-safety representative will complete the risk and accessibility assessment by Week 8 and close critical findings before occupation. HR and Internal Communications will issue practical move and access guidance by Week 9, provide employee briefings in Week 10, and confirm first-aiders, fire wardens, evacuation routes, and workstation setup before the first operating day.
Medium

Budget Overrun and Schedule Compression

If hidden fit-out works, replacement furniture, expedited delivery, overlapping premises costs, disposal charges, or late purchase orders exceed the approved reserve or are identified after Week 6, the project may exceed the EUR 110,000 budget or miss the end-of-Q2 deadline.

Countermeasure: Finance and Procurement will establish the cost baseline and approval thresholds in Week 1, obtain competitive quotations by Week 4, place long-lead orders by Week 6, and issue a weekly forecast against the budget. The Executive Sponsor will approve or reject scope changes, and the Project Manager will preserve the contingency reserve for defined risks only.

Stakeholders

ES

Executive Sponsor

Approves budget, scope changes, and deadline trade-offs

Involve: Phase 1
PM

Project Manager or Office Manager

Coordinates the integrated plan, decisions, vendors, and issue resolution

Involve: Phase 1
IA

IT and Telecommunications Lead

Owns connectivity, devices, telephony, access permissions, backups, and cutover testing

Involve: Phase 1
FO

Facilities or Workplace Lead

Owns site readiness, layout, utilities, furniture, health and safety, and landlord coordination

Involve: Phase 1
HA

HR and Internal Communications

Coordinates employee information, attendance arrangements, policies, and change support

Involve: Phase 2
DR

Department Representatives

Identify business-critical equipment, customer-facing constraints, and team-specific workspace needs

Involve: Phase 2
FA

Finance and Procurement

Controls budget, purchasing, contracts, deposits, and supplier approvals

Involve: Phase 1
MF

Moving, Fit-Out, and Building-Service Suppliers

Execute packing, transport, installation, cleaning, access, and building-readiness activities

Involve: Phase 2

Compliance

Mandatory

Confirm lease, landlord, insurance, building-access, fit-out, reinstatement, and occupation obligations before works and the move.

Facilities or Workplace Lead with Finance and Procurement Weeks 2–6
Mandatory

Maintain asset inventories, chain-of-custody records, restricted access, secure transport, backup verification, and incident escalation for business equipment and information.

IT and Telecommunications Lead with Information Security and the Project Manager Weeks 7–11
Mandatory

Complete employee consultation, contractual notification, working-location updates, and remote-working or temporary-work arrangements where required by applicable employment law and company policy.

HR and Internal Communications Weeks 2–10
Optional

Perform documented business-continuity, backup-and-restore, cutover, and fallback testing consistent with the organization’s continuity and information-security policies, including relevant ISO 22301 or ISO 27001 controls where adopted.

IT and Telecommunications Lead with the Project Manager Weeks 7–10
Mandatory

Ensure suppliers have approved contracts, confidentiality obligations, appropriate insurance, safe-working procedures, and compliant disposal arrangements for waste electrical equipment and confidential materials.

Finance and Procurement with Facilities and IT Weeks 4–10
Optional

Retain project approvals, readiness evidence, safety assessments, test results, asset reconciliations, supplier records, and post-move incident logs for the organization’s required audit and records-retention period.

Project Manager with Finance, HR, IT, and Facilities Weeks 1–11 and post-move closeout

Milestones

  1. Week 1

    Approved project charter, requirements register, decision structure, and initial budget baseline

    Depends on: Project initiation and stakeholder alignment
  2. Week 3

    Site-readiness assessment and approved remediation plan with owners, costs, and completion dates

    Depends on: New-site due diligence and readiness review
  3. Week 6

    Approved workplace layout, contracted moving supplier, procurement orders placed, and detailed integrated move plan issued

    Depends on: Workplace design, procurement, and move planning
  4. Week 9

    New site passes the integrated IT, facilities, access-control, safety, and workplace readiness acceptance test

    Depends on: IT, telecom, and facilities preparation
  5. Week 10

    Employees briefed, assets packed and reconciled, cutover rehearsal completed, and approved move-day runbook issued

    Depends on: Communications, packing, and cutover rehearsal
  6. Week 11

    All 60 employees are operational at the new building, critical services have passed acceptance testing, and no unresolved critical disruption remains

    Depends on: Move execution and stabilization

How this plan was created

This plan was created by PathHub AI from a single description: “Move our office with 60 employees to a new building by the end of Q2, without disrupting operations.” — without company context. With your departments, approval processes and compliance requirements it becomes much more precise.

Obligations

Obligations with lead time: what many think of too late

These obligations are typically triggered by an office move (example: Germany). PathHub AI schedules them with lead time, warns when the schedule is too tight and shows the rule with its criteria under “Rule & evidence”, which you tick off and back with evidence. Not legal advice.

Prepare and document the risk assessment of the new workplace (Sec. 3 ArbStättV)
Required 2–4 weeks before the movestatutory
Rule & evidence

Why: New premises mean new escape routes, lighting, ventilation and workstations.

Legal basis: Sec. 3 ArbStättV: the risk assessment must be documented before work begins.

Rule from the compliance library
Workplace Ordinance (ArbStättV)
Criteria
  • Workplace risk assessment documented before work begins (Sec. 3)
  • Escape and rescue routes, emergency exits and signage (ASR A2.3)
  • Lighting, ventilation and room temperature according to the ASR
  • Ergonomic display screen workstations
  • Sanitary, break and first-aid rooms according to headcount

If breached: Administrative offence with fines up to EUR 5,000 per violation (Sec. 9 ArbStättV with Sec. 25 ArbSchG); intentionally endangering life or health is a criminal offence.

Evidence: In PathHub you tick off the criteria and attach evidence to each item as a file, link or note. Everything exports as a PDF evidence report.
Instruct employees at the new site on escape routes and procedures (Sec. 12 ArbSchG)
Required up to 1 week before the movestatutory
Rule & evidence

Why: Instruction is mandatory when working conditions change.

Legal basis: Sec. 12 ArbSchG: instruction on changes before work begins.

Rule from the compliance library
Occupational Health and Safety Act
Criteria
  • Risk assessment for every workstation (incl. psychological stress)
  • Instruction on hiring, after changes, after accidents — at least annually
  • Safety officer and company doctor appointed (DGUV V2)
  • First-aid responders (min. 5% of staff) trained

If breached: Fines up to EUR 30,000 per violation (Sec. 25 ArbSchG); persistent repetition or intentional endangerment: imprisonment up to one year or a fine (Sec. 26). Personal injury can additionally lead to criminal liability under the Criminal Code.

Evidence: In PathHub you tick off the criteria and attach evidence to each item as a file, link or note. Everything exports as a PDF evidence report.
Inform the works council and attempt a reconciliation of interests on the relocation (Sec. 111 BetrVG)
Important 8–16 weeks before the moveguide value
Rule & evidence

Why: A relocation changes commutes, workstations and procedures.

Applies: if a works council exists; reconciliation of interests for relocating the establishment in companies with more than 20 eligible employees

Legal basis: Sec. 111 sentence 3 No. 2 BetrVG: relocating the establishment is an operational change; a reconciliation of interests must be attempted beforehand.

Rule from the compliance library
Works Constitution Act (BetrVG)
Criteria
  • Enable works council election from 5 eligible employees upward
  • Co-determination on working time, monitoring systems, IT rollouts (§87)
  • Hearing before every dismissal (§102) — written with reasons
  • Balance-of-interests and social plan on operational changes (§111)

If breached: Dismissals without works council hearing are void. Administrative fines up to €10,000 per violation. Criminal liability (§119) for obstructing the works council up to 1 year imprisonment.

Evidence: In PathHub you tick off the criteria and attach evidence to each item as a file, link or note. Everything exports as a PDF evidence report.
Move files and storage media in a data-protection-compliant way or have them destroyed according to DIN 66399
Important 1–2 weeks before the moveguide value
Rule & evidence

Why: During a move, documents with personal data pass through many hands.

Rule from the compliance library
GDPR (General Data Protection Regulation)
Criteria
  • Legal basis for every processing of personal data (consent, contract, legal obligation, legitimate interest)
  • Complete record of processing activities (Art. 30) for all processes
  • Data Processing Agreements (DPA) with all sub-processors
  • Data Protection Impact Assessment (DPIA) for high-risk processing
  • Technical and organisational measures (TOM) documented

If breached: Fines up to €20 million or 4% of global annual revenue — whichever is higher. Plus civil damages claims by affected individuals.

Evidence: In PathHub you tick off the criteria and attach evidence to each item as a file, link or note. Everything exports as a PDF evidence report.
All typical initiatives and their obligations: planning internal projects

Frequently asked questions

How long does an office move take?
In the example plan, an office move takes 11 weeks in 6 phases, of which 1 phases partly run in parallel. The actual duration depends on company size, starting point and available resources — with your company context PathHub adjusts the schedule accordingly.
What does an office move cost?
The example plan estimates about €98,000, split into 15 budget line items with quantity and unit price. The largest items are IT, Network, Telephony & Access Control, Premises Preparation & Minor Fit-Out. This is an AI estimate as a starting point, not a quote.
What are the risks of an office move?
The plan lists 6 risks with countermeasures. Rated highest: New-Building Readiness and Approval Delay; IT, Telecom, and Access-Control Cutover Failure; Loss, Damage, or Unauthorized Disclosure of Personal and Business Data.
Who needs to be involved in an office move?
Among others, the plan includes these people: Executive Sponsor, Project Manager or Office Manager, IT and Telecommunications Lead, Facilities or Workplace Lead, HR and Internal Communications, Department Representatives. For each role it states why and from when to involve them.
Can I adapt the plan to my company?
Yes. Open the plan in PathHub without signing up, adjust phases and tasks or describe your own initiative — with company context (departments, approval processes, works council, compliance requirements) every further plan gets more precise.