Project plan for an office move
An office move project plan coordinates six phases over 11 weeks to relocate 60 employees while maintaining business continuity within an approximate €98,000 budget. The plan covers requirements, site readiness, workplace design, procurement, IT and telecom preparation, communications, packing, move execution, risks, stakeholders, and compliance. PathHub AI organizes 31 tasks with owners, schedules, dependencies, and a low-disruption cutover.
- 11 Weeks
- 6 Phases
- 31 Tasks
- Budget approx. €98,000
No sign-up · opens instantly
Your own project? The AI project plan generator builds a plan like this from a short description.
This is how the plan looks in PathHub. Pick a tab or open the plan live to tick off tasks and edit everything.






The plan in detail
Everything in the example plan to read through. In the live plan you can take it over and adapt it.
Phases and tasks
Phase 1: Initiation and Requirements Definition
Establish the relocation mandate, decision rights, requirements, budget baseline, and operational constraints for moving 60 employees by the end of Q2. This creates the governance and acceptance criteria needed to protect business continuity.
- Important Run the project kickoff and approve the project charter covering scope, end-of-Q2 deadline, no-disruption criteria, escalation routes, and decision rightsExecutive Sponsor and Project Manager or Office Manager · 2 days
- Conduct departmental requirements workshops covering headcount, critical equipment, customer-facing activities, storage needs, meeting-room requirements, and move restrictionsProject Manager or Office Manager and Department Representatives · 3 days
- Establish the initial budget baseline, procurement approach, approval thresholds, decision log, and integrated stakeholder contact listFinance and Procurement and Project Manager or Office Manager · 2 days
Phase 2: New-Site Due Diligence and Readiness Planning
Confirm that the new building can safely and practically support 60 employees, including required capacity, utilities, connectivity, access, and building services. Identify readiness gaps early enough to complete corrective works before the move.
- Important Complete a building-readiness inspection covering capacity, lease obligations, fire and health-and-safety requirements, loading access, utilities, landlord works, and occupancy constraintsFacilities or Workplace Lead and Building-Service Suppliers · 5 days
- Survey the new site’s electrical capacity, network cabling, telecom demarcation, Wi-Fi coverage requirements, access-control points, and backup-connectivity optionsIT and Telecommunications Lead and Facilities or Workplace Lead · 4 days
- Produce a site-readiness gap register with corrective actions, owners, dependencies, target dates, and contingency triggersFacilities or Workplace Lead and Project Manager or Office Manager · 3 days
- Obtain and compare supplier quotations for minor fit-out, connectivity, access control, cleaning, security, utilities, and disposal servicesFinance and Procurement · 4 days
- Confirm the proposed occupancy capacity and preliminary department zoning against the requirements register for all 60 employeesFacilities or Workplace Lead and Department Representatives · 3 days
- Important Maintain asset inventories, chain-of-custody records, restricted access, secure transport, backup verification, and incident escalation for business equipment and information.IT and Telecommunications Lead with Information Security and the Project Manager · 3 days
Phase 3: Workplace Design, Procurement, and Move Planning
Convert the site requirements into an approved workplace design, confirmed supplier arrangements, asset plan, and detailed move schedule. This phase ensures that every employee, workstation, asset, and move activity has a defined destination and owner.
- Finalize the seating plan for 60 employees, department zones, meeting rooms, storage, reception, accessibility provisions, and ergonomic requirementsFacilities or Workplace Lead and Department Representatives · 5 days
- Complete an asset inventory covering workstations, monitors, phones, printers, furniture, confidential records, and items for reuse, disposal, or replacementIT and Telecommunications Lead and Facilities or Workplace Lead · 4 days
- Important Appoint the moving supplier and issue a detailed statement of work covering packing, transport, insurance, chain of custody, loading access, installation, and the agreed low-impact move windowFinance and Procurement and Project Manager or Office Manager · 4 days
- Procure approved furniture, ergonomic items, signage, packing materials, storage equipment, and meeting-room equipmentFinance and Procurement and Facilities or Workplace Lead · 5 days
- Build the integrated move schedule linking landlord works, fit-out, connectivity, furniture delivery, access-control setup, packing, transport, and operational acceptanceProject Manager or Office Manager and Facilities or Workplace Lead · 4 days
- Create the room-by-room move map, asset labels, workstation assignments, department ownership list, and delivery sequenceProject Manager or Office Manager and Moving, Fit-Out, and Building-Service Suppliers · 3 days
Phase 4: IT, Telecom, and Facilities Preparation
Make the new site operational before the physical move by completing fit-out, connectivity, access control, furniture installation, and device preparation. All essential services must be tested together rather than relying on individual supplier completion.
- Important Install and validate internet connectivity, LAN, Wi-Fi, VLANs, network cabinets, cabling, and network capacity for 60 workstations and meeting roomsIT and Telecommunications Lead and Building-Service Suppliers · 8 days
- Configure and test telephone number porting, handsets or softphones, call routing, voicemail, and temporary fallback telephonyIT and Telecommunications Lead · 5 days
- Install access-control hardware, issue employee badges, configure permissions, and test visitor and out-of-hours access proceduresFacilities or Workplace Lead and Building-Service Suppliers · 3 days
- Important Complete minor fit-out works including power adjustments, cabling changes, partitions, signage, repairs, and required landlord worksFacilities or Workplace Lead and Fit-Out Suppliers · 8 days
- Deliver and install desks, chairs, storage, meeting-room equipment, reception items, and approved ergonomic adjustmentsFacilities or Workplace Lead and Moving, Fit-Out, and Building-Service Suppliers · 5 days
- Stage and test 60 employee workstations, printers, meeting-room devices, endpoint configurations, backups, and secure asset trackingIT and Telecommunications Lead · 6 days
- Complete the facilities acceptance inspection covering cleaning, utilities, fire safety, emergency signage, waste arrangements, security, and outstanding defectsFacilities or Workplace Lead and Building-Service Suppliers · 3 days
Phase 5: Communications, Packing, and Cutover Rehearsal
Prepare employees and physical assets for the move while validating the operational cutover in advance. The rehearsal confirms fallback arrangements for connectivity, telephony, access, devices, and critical business activities.
- Important Issue the employee communications pack with move dates, seating assignments, packing instructions, access procedures, remote-working arrangements, safety guidance, and support contactsHR and Internal Communications · 3 days
- Distribute department-specific labels and packing kits, pack non-essential files and equipment, and reconcile packed items against the asset registerMoving, Fit-Out, and Building-Service Suppliers and Department Representatives · 4 days
- Securely pack critical IT equipment, confidential documents, and business records using documented chain-of-custody controls and confirmed backupsIT and Telecommunications Lead and Department Representatives · 3 days
- Important Rehearse the cutover using the fallback network, temporary telephony, access procedures, device recovery steps, and escalation contacts; record and close defectsIT and Telecommunications Lead and Project Manager or Office Manager · 3 days
- Finalize the move-day runbook covering supplier arrival times, loading access, transport sequence, room placement, contact tree, floor wardens, contingency actions, and acceptance checksProject Manager or Office Manager and Moving, Fit-Out, and Building-Service Suppliers · 2 days
Phase 6: Move Execution and Stabilization
Execute the physical move during the lowest-impact window, activate the new office, and stabilize operations for all 60 employees. The phase ends only after critical services and departmental operations have been formally accepted.
- Important Execute the physical move during the approved low-impact window, transporting and installing assets according to the room map and chain-of-custody recordsMoving, Fit-Out, and Building-Service Suppliers and Facilities or Workplace Lead · 2 days
- Activate and validate network connectivity, telephony, access badges, printers, meeting-room systems, endpoint devices, and other critical services at the new siteIT and Telecommunications Lead · 1 day
- Conduct first-day operational acceptance with each department, record defects, assign owners, and resolve any critical access, connectivity, equipment, or workplace issuesProject Manager or Office Manager and Department Representatives · 2 days
- Complete old-site closure activities, including final cleaning, waste and disposal confirmation, key return, utility handover, supplier sign-off, and final invoice reconciliationFacilities or Workplace Lead and Finance and Procurement · 2 days
Budget
| Item | Quantity | Unit price | Total |
|---|---|---|---|
| Internal Personnel & Governance | |||
| Project Manager / Office Manager, including supplier and move coordination | 15 Person days | €900 | €13,500 |
| Finance and Procurement Coordinator | 4 Person days | €500 | €2,000 |
| Premises Preparation & Minor Fit-Out | |||
| Site Readiness and Health & Safety Consultant | 3 Person days | €1,000 | €3,000 |
| Electrical, cabling, minor partitions, repairs and signage | 1 Flat rate | €15,000 | €15,000 |
| IT, Network, Telephony & Access Control | |||
| Structured Network Installation and Testing | 1 Flat rate | €9,000 | €9,000 |
| Internet Circuit and Telecom Activation | 1 Flat rate | €4,500 | €4,500 |
| IT Workstation, Telephony and Access-Control Cutover Engineer | 9 Person days | €1,000 | €9,000 |
| Professional Moving, Packing & Transport | |||
| Professional Moving Crew | 20 Person days | €450 | €9,000 |
| Packing Materials, Asset Labels and Secure Packing Supplies | 1 Flat rate | €3,000 | €3,000 |
| Transport, Furniture Handling, Transit Insurance and Disposal | 1 Flat rate | €5,500 | €5,500 |
| Furniture & Workplace Equipment | |||
| Additional Desks and Office Chairs | 10 Person days | €700 | €7,000 |
| Storage, Meeting-Room and Ergonomic Equipment | 8 Person days | €500 | €4,000 |
| Security, Cleaning, Utilities & Employee Operations | |||
| Final Cleaning, Waste Removal, Security Administration and Overlapping Utilities | 1 Flat rate | €6,500 | €6,500 |
| Employee Communications, Briefings and Move Instructions | 8 Person days | €250 | €2,000 |
| Temporary Workspace, Move-Day Supplies and Contingency Operations | 1 Flat rate | €5,000 | €5,000 |
| Sum of items | €98,000 | ||
Risks
New-Building Readiness and Approval Delay
High impactIf landlord works, cabling, utilities, access permissions, fire-safety documentation, or occupancy approvals are not complete and accepted by the end of Week 8, the move window may be compressed or the building may be unsuitable for occupation by the end of Q2.
Countermeasure: The Facilities or Workplace Lead will complete site due diligence by Week 3, agree a remediation plan with the landlord by Week 4, track evidence of completion weekly, and conduct a formal building-readiness go/no-go review by Week 9. The Project Manager will maintain temporary workspace or remote-working capacity as a contingency.
IT, Telecom, and Access-Control Cutover Failure
High impactIf network connectivity, Wi-Fi, VPN, telephony, access control, workstations, or essential business applications fail integrated testing by Week 9, employees may be unable to work effectively on the first business day at the new site.
Countermeasure: The IT and Telecommunications Lead will complete installation and component testing by Week 8, perform integrated acceptance testing by Week 9, and conduct a cutover rehearsal in Week 10. IT will prepare verified backups, temporary connectivity, call-forwarding, remote-working support, and a documented rollback and incident-response procedure before the move.
Loss, Damage, or Unauthorized Disclosure of Personal and Business Data
High impactIf laptops, documents, storage media, credentials, or access badges are not inventoried, secured, and reconciled before transport in Week 10, equipment could be lost or damaged and personal or confidential information could be exposed during packing or the move.
Countermeasure: The IT Lead, HR, and the data-protection or information-security owner will complete an asset and data inventory by Week 9, apply tamper-evident labels and sealed containers, restrict handling to authorized movers, maintain chain-of-custody records, and reconcile all assets by the end of Week 11. Unneeded records and equipment will be securely destroyed through approved providers.
Moving Supplier or Loading-Window Failure
Medium impactIf the mover, lift access, loading bay, building access permissions, insurance, or transport route are not confirmed by Week 6, the move may be delayed, incur additional charges, or result in damage to furniture and equipment.
Countermeasure: Procurement and the Project Manager will contract the primary mover and confirm insurance, access arrangements, staffing, vehicle capacity, and loading windows by Week 6. The Facilities Lead will complete a route and loading survey by Week 7, while the Project Manager will retain a backup supplier or alternative move window before Week 9.
Workplace Health, Safety, Accessibility, and Employee Readiness Gaps
Medium impactIf the workplace risk assessment, emergency arrangements, accessibility checks, ergonomic setup, employee instructions, or evacuation roles are incomplete by Week 9, the move could create safety incidents, non-compliance, reduced productivity, or employee resistance.
Countermeasure: The Facilities Lead and applicable health-and-safety representative will complete the risk and accessibility assessment by Week 8 and close critical findings before occupation. HR and Internal Communications will issue practical move and access guidance by Week 9, provide employee briefings in Week 10, and confirm first-aiders, fire wardens, evacuation routes, and workstation setup before the first operating day.
Budget Overrun and Schedule Compression
Medium impactIf hidden fit-out works, replacement furniture, expedited delivery, overlapping premises costs, disposal charges, or late purchase orders exceed the approved reserve or are identified after Week 6, the project may exceed the EUR 110,000 budget or miss the end-of-Q2 deadline.
Countermeasure: Finance and Procurement will establish the cost baseline and approval thresholds in Week 1, obtain competitive quotations by Week 4, place long-lead orders by Week 6, and issue a weekly forecast against the budget. The Executive Sponsor will approve or reject scope changes, and the Project Manager will preserve the contingency reserve for defined risks only.
Stakeholders
Executive Sponsor
Approves budget, scope changes, and deadline trade-offs
Involve: Phase 1
Project Manager or Office Manager
Coordinates the integrated plan, decisions, vendors, and issue resolution
Involve: Phase 1
IT and Telecommunications Lead
Owns connectivity, devices, telephony, access permissions, backups, and cutover testing
Involve: Phase 1
Facilities or Workplace Lead
Owns site readiness, layout, utilities, furniture, health and safety, and landlord coordination
Involve: Phase 1
HR and Internal Communications
Coordinates employee information, attendance arrangements, policies, and change support
Involve: Phase 2
Department Representatives
Identify business-critical equipment, customer-facing constraints, and team-specific workspace needs
Involve: Phase 2
Finance and Procurement
Controls budget, purchasing, contracts, deposits, and supplier approvals
Involve: Phase 1
Moving, Fit-Out, and Building-Service Suppliers
Execute packing, transport, installation, cleaning, access, and building-readiness activities
Involve: Phase 2
Obligations and compliance
| Requirement | Owner | Timing | Type |
|---|---|---|---|
| Confirm lease, landlord, insurance, building-access, fit-out, reinstatement, and occupation obligations before works and the move. | Facilities or Workplace Lead with Finance and Procurement | Weeks 2–6 | Mandatory |
| Maintain asset inventories, chain-of-custody records, restricted access, secure transport, backup verification, and incident escalation for business equipment and information. | IT and Telecommunications Lead with Information Security and the Project Manager | Weeks 7–11 | Mandatory |
| Complete employee consultation, contractual notification, working-location updates, and remote-working or temporary-work arrangements where required by applicable employment law and company policy. | HR and Internal Communications | Weeks 2–10 | Mandatory |
| Perform documented business-continuity, backup-and-restore, cutover, and fallback testing consistent with the organization’s continuity and information-security policies, including relevant ISO 22301 or ISO 27001 controls where adopted. | IT and Telecommunications Lead with the Project Manager | Weeks 7–10 | Important |
| Ensure suppliers have approved contracts, confidentiality obligations, appropriate insurance, safe-working procedures, and compliant disposal arrangements for waste electrical equipment and confidential materials. | Finance and Procurement with Facilities and IT | Weeks 4–10 | Mandatory |
| Retain project approvals, readiness evidence, safety assessments, test results, asset reconciliations, supplier records, and post-move incident logs for the organization’s required audit and records-retention period. | Project Manager with Finance, HR, IT, and Facilities | Weeks 1–11 and post-move closeout | Important |
Milestones
| Week | Milestone | Prerequisite |
|---|---|---|
| 1 | Approved project charter, requirements register, decision structure, and initial budget baseline | Project initiation and stakeholder alignment |
| 3 | Site-readiness assessment and approved remediation plan with owners, costs, and completion dates | New-site due diligence and readiness review |
| 6 | Approved workplace layout, contracted moving supplier, procurement orders placed, and detailed integrated move plan issued | Workplace design, procurement, and move planning |
| 9 | New site passes the integrated IT, facilities, access-control, safety, and workplace readiness acceptance test | IT, telecom, and facilities preparation |
| 10 | Employees briefed, assets packed and reconciled, cutover rehearsal completed, and approved move-day runbook issued | Communications, packing, and cutover rehearsal |
| 11 | All 60 employees are operational at the new building, critical services have passed acceptance testing, and no unresolved critical disruption remains | Move execution and stabilization |
How this plan was created
This plan was created by PathHub AI from a single description: “Move our office with 60 employees to a new building by the end of Q2, without disrupting operations.” Without company context. With your departments, approval processes and compliance requirements it becomes much more precise.
Obligations with lead time: what many think of too late
These obligations are typically triggered by an office move (example: Germany). PathHub AI schedules them with lead time, warns when the schedule is too tight and shows the rule with its criteria under “Rule & evidence”, which you tick off and back with evidence. Not legal advice.
Rule & evidence
Why: New premises mean new escape routes, lighting, ventilation and workstations.
Legal basis: Sec. 3 ArbStättV: the risk assessment must be documented before work begins.
- Workplace risk assessment documented before work begins (Sec. 3)
- Escape and rescue routes, emergency exits and signage (ASR A2.3)
- Lighting, ventilation and room temperature according to the ASR
- Ergonomic display screen workstations
- Sanitary, break and first-aid rooms according to headcount
If breached: Administrative offence with fines up to EUR 5,000 per violation (Sec. 9 ArbStättV with Sec. 25 ArbSchG); intentionally endangering life or health is a criminal offence.
Rule & evidence
Why: Instruction is mandatory when working conditions change.
Legal basis: Sec. 12 ArbSchG: instruction on changes before work begins.
- Risk assessment for every workstation (incl. psychological stress)
- Instruction on hiring, after changes, after accidents: at least annually
- Safety officer and company doctor appointed (DGUV V2)
- First-aid responders (min. 5% of staff) trained
If breached: Fines up to EUR 30,000 per violation (Sec. 25 ArbSchG); persistent repetition or intentional endangerment: imprisonment up to one year or a fine (Sec. 26). Personal injury can additionally lead to criminal liability under the Criminal Code.
Rule & evidence
Why: A relocation changes commutes, workstations and procedures.
Applies: if a works council exists; reconciliation of interests for relocating the establishment in companies with more than 20 eligible employees
Legal basis: Sec. 111 sentence 3 No. 2 BetrVG: relocating the establishment is an operational change; a reconciliation of interests must be attempted beforehand.
- Enable works council election from 5 eligible employees upward
- Co-determination on working time, monitoring systems, IT rollouts (§87)
- Hearing before every dismissal (§102): written with reasons
- Balance-of-interests and social plan on operational changes (§111)
If breached: Dismissals without works council hearing are void. Administrative fines up to €10,000 per violation. Criminal liability (§119) for obstructing the works council up to 1 year imprisonment.
Rule & evidence
Why: During a move, documents with personal data pass through many hands.
- Legal basis for every processing of personal data (consent, contract, legal obligation, legitimate interest)
- Complete record of processing activities (Art. 30) for all processes
- Data Processing Agreements (DPA) with all sub-processors
- Data Protection Impact Assessment (DPIA) for high-risk processing
- Technical and organisational measures (TOM) documented
If breached: Fines up to €20 million or 4% of global annual revenue, whichever is higher. Plus civil damages claims by affected individuals.