Example project plan

Project plan for an SAP S/4HANA implementation

An SAP S/4HANA implementation project plan for this brownfield conversion spans 52 weeks, with 14 phases, 122 tasks, and an approximate €3,696,000 budget. It covers governance, assessment, readiness, custom code, integrations, data quality, testing, training, go-live, and hypercare for a 900-employee manufacturer using FI/CO, MM, SD, and PP.

  • 52 Weeks
  • 14 Phases
  • 122 Tasks
  • Budget approx. €3,696,000

No sign-up · opens instantly

Your own project? The AI project plan generator builds a plan like this from a short description.

This is how the plan looks in PathHub. Pick a tab or open the plan live to tick off tasks and edit everything.

app.pathhub.ai/try?example=sap-enOpen live
PathHub view “Overview” of the example plan SAP ECC to SAP S/4HANA Brownfield Conversion
Progress, time, budget, risks and obligations at a glance, plus the next tasks and AI hints.

The plan in detail

Everything in the example plan to read through. In the live plan you can take it over and adapt it.

Phases and tasks

Phase 1: Program Mobilization and Governance

Week 1–3 · 5 tasks · Owner: SAP Program Director / Program Manager

Establish the governance model, delivery standards, workstream structure and decision rights for the brownfield conversion. This creates the control framework required to manage the fiscal-year go-live and cross-functional dependencies.

  • Important Approve the program charter covering FI/CO, MM, SD, PP, plants, interfaces, custom code and fiscal-year go-live objectivesExecutive Sponsor / Steering Committee · 3 days
  • Establish the steering committee, project management office, workstream forums and escalation pathsSAP Program Director / Program Manager · 4 days
  • Nominate workstream leads and define the RACI matrix for finance, procurement, sales, manufacturing, data, testing, technology and changeSAP Program Director / Program Manager · 5 days
  • Set up the integrated plan, RAID log, change-control process, document repository and status-reporting templatesSAP Program Director / Program Manager · 4 days
  • Confirm resource commitments from internal departments, plants, SAP Basis, business key users and the external SAP Systems IntegratorCIO or Head of IT · 4 days

Phase 2: Current-State Assessment and Scope Confirmation

Week 4–8 · 8 tasks · Owner: SAP Program Director / Program Manager

Establish a fact-based baseline of the ECC solution, business processes, plants, interfaces, data objects, reports and custom developments. The phase confirms what will be converted, redesigned, retired or excluded from the S/4HANA scope.

  • Important Document the current FI/CO, MM, SD and PP process baseline across all legal entities, plants and distribution locationsFinance Transformation Lead, Procurement and Materials Management Lead, Sales and Distribution Lead, Production Planning and Manufacturing Lead · 8 days
  • Capture transaction volumes, month-end and year-end activities, MRP runs, production scheduling windows, warehouse peaks and critical batch jobsSAP Basis and Infrastructure Lead · 6 days
  • Important Inventory ECC custom programs, enhancements, modifications, user exits, forms, workflows, reports, interfaces, add-ons and background jobsABAP and Custom Code Lead · 8 days
  • Map master data and transactional data objects, retention requirements and historical reporting dependencies for materials, customers, suppliers, finance and productionData Migration and Master Data Owner · 6 days
  • Assess current integrations with MES, EDI partners, warehouse systems, CRM, banks, tax services, logistics providers and other external platformsEnterprise Architecture and Integration Lead · 7 days
  • Identify current authorization roles, segregation-of-duties conflicts, critical access paths and audit-control dependenciesInformation Security, Internal Controls and Compliance Representatives · 5 days
  • Document business pain points, manual workarounds, plant-specific variants and known ECC process deviationsPlant Managers and Business Key Users · 7 days
  • Confirm in-scope legal entities, plants, modules, interfaces, historical data, reports and organizational units through a signed scope baselineSAP Program Director / Program Manager · 4 days

Phase 3: S/4HANA Readiness and Technical Assessment

Week 5–10 · 9 tasks · Owner: SAP Basis and Infrastructure Lead

Determine whether the ECC landscape, custom developments, add-ons, infrastructure, interfaces and security model are ready for conversion. The output is a prioritized remediation backlog with clear technical and business decisions.

  • Important Execute SAP Readiness Check and simplification-item analysis for the selected S/4HANA release, including mandatory finance, logistics and technical changesSAP Systems Integrator · 5 days
  • Important Run ATC and custom-code analysis against the complete ECC code inventory and classify findings by business criticality, remediation effort and retirement potentialABAP and Custom Code Lead · 10 days
  • Assess the compatibility and S/4HANA support status of SAP add-ons, industry solutions, third-party tools and plug-insSAP Basis and Infrastructure Lead · 5 days
  • Develop the target infrastructure, database, storage, network, backup and disaster-recovery sizing for development, quality and production environmentsSAP Basis and Infrastructure Lead · 7 days
  • Review interface technologies, IDocs, RFCs, APIs, middleware mappings, EDI formats, certificates and monitoring capabilities for S/4HANA compatibilityEnterprise Architecture and Integration Lead · 8 days
  • Assess data conversion complexity for business partners, material master, inventory, open items, assets, production master data and historical transactionsData Migration and Master Data Owner · 6 days
  • Baseline authorization, segregation-of-duties, sensitive transactions, technical users and audit requirements against the target S/4HANA modelInformation Security, Internal Controls and Compliance Representatives · 5 days
  • Define the target system landscape, client strategy, transport path, conversion tooling and refresh approach for all project environmentsSAP Basis and Infrastructure Lead · 6 days
  • Consolidate technical findings into a readiness report with decisions, owners, due dates, assumptions and prerequisites for the conversionSAP Program Director / Program Manager · 4 days

Phase 4: Fit-to-Standard and Solution Design

Week 9–16 · 10 tasks · Owner: SAP Systems Integrator

Define the target S/4HANA process design using standard capabilities wherever possible and formally approve only justified deviations. The phase aligns finance, supply chain, sales, manufacturing, reporting, security and plant requirements before build activities begin.

  • Important Conduct FI/CO fit-to-standard workshops covering the universal journal, controlling objects, allocations, asset accounting, period close, budgeting and management reportingCFO and Finance Transformation Lead · 6 days
  • Conduct MM fit-to-standard workshops covering purchasing, inventory management, valuation, supplier processes, goods movements and invoice verificationProcurement and Materials Management Lead · 5 days
  • Conduct SD fit-to-standard workshops covering customer master, pricing, order management, delivery, shipping, billing and credit processesSales and Distribution Lead · 5 days
  • Important Conduct PP and plant fit-to-standard workshops covering BOMs, routings, work centers, MRP, capacity planning, production orders, confirmations and shop-floor executionProduction Planning and Manufacturing Lead · 7 days
  • Important Validate cross-module scenarios for procure-to-pay, order-to-cash, plan-to-produce, inventory valuation and record-to-reportSAP Systems Integrator · 6 days
  • Define the target reporting, analytics, forms, output management and statutory reporting approach for finance and operationsCFO and Finance Transformation Lead · 5 days
  • Design the target authorization roles, approval workflows and segregation-of-duties controls for business and plant rolesInformation Security, Internal Controls and Compliance Representatives · 6 days
  • Document plant-specific requirements, approved deviations, retained ECC behaviors and process harmonization decisionsPlant Managers and Business Key Users · 7 days
  • Define target integration patterns for MES, EDI, warehouse, banking, CRM, tax and logistics interfacesEnterprise Architecture and Integration Lead · 5 days
  • Produce and approve the solution blueprint, process decision log, fit-gap register and signed design authority decisionsSAP Program Director / Program Manager · 5 days

Phase 5: Custom Code Remediation

Week 10–18 · 12 tasks · Owner: ABAP and Custom Code Lead

Remediate custom developments affected by S/4HANA simplification items, changed data models, obsolete transactions and revised integration patterns. Obsolete or low-value developments are retired to reduce conversion risk and future maintenance effort.

  • Important Prioritize the custom-code backlog using business criticality, usage frequency, conversion impact, plant dependency and retirement feasibilityABAP and Custom Code Lead · 4 days
  • Remediate FI/CO developments affected by the universal journal, business partner model, asset accounting, controlling tables and changed financial data structuresABAP and Custom Code Lead · 10 days
  • Remediate MM developments covering purchasing, inventory, valuation, material documents, supplier data and goods-movement processingABAP and Custom Code Lead · 9 days
  • Remediate SD developments covering business partners, pricing, deliveries, billing, outputs, credit management and customer interfacesABAP and Custom Code Lead · 9 days
  • Important Remediate PP and manufacturing developments covering BOMs, routings, MRP, production orders, confirmations, capacity and plant-specific transactionsABAP and Custom Code Lead · 11 days
  • Replace obsolete custom interfaces, reports, forms, workflows and transactions with approved S/4HANA standard functions, APIs or extension patternsSAP Systems Integrator · 9 days
  • Retire unused, duplicate or unsupported custom objects and document the technical and business approval for each retirementABAP and Custom Code Lead · 5 days
  • Important Execute developer unit tests and technical regression tests for all remediated, redesigned and retained custom objectsABAP and Custom Code Lead · 9 days
  • Run repeated ATC scans, syntax checks, performance checks and code-quality reviews against the selected S/4HANA releaseSAP Systems Integrator · 6 days
  • Validate remediation of critical background jobs, extracts, forms and month-end programs with their business ownersTest and Quality Manager · 7 days
  • Release the remediated code package into the integration backlog with traceability from finding to transport and test evidenceSAP Program Director / Program Manager · 4 days
  • Important Confirm SAP licensing, S/4HANA subscription or maintenance rights, third-party add-on compatibility, interface-provider contracts and EDI partner obligations before production conversion.CIO, Procurement Lead, SAP Licensing Owner and Enterprise Architecture Lead · 3 days

Phase 6: Architecture, Integration and Data Migration Design

Week 13–19 · 9 tasks · Owner: Enterprise Architecture and Integration Lead

Finalize the target architecture, integration design, migration objects, ownership model and reconciliation controls. This phase converts the solution blueprint into build-ready technical specifications and measurable data-quality requirements.

  • Important Approve the target S/4HANA architecture, system landscape, connectivity, security zones, resilience model, monitoring and operational ownershipEnterprise Architecture and Integration Lead · 6 days
  • Create the detailed interface catalog with source, target, protocol, frequency, data owner, error handling, monitoring and cutover dependency for every integrationEnterprise Architecture and Integration Lead · 8 days
  • Define API, IDoc, RFC, middleware, EDI, certificate and message-mapping specifications for MES, warehouse, banks, tax, CRM and logistics partnersEnterprise Architecture and Integration Lead · 8 days
  • Create the migration-object inventory and mapping specifications for business partners, materials, suppliers, customers, assets, open items, inventory and production master dataData Migration and Master Data Owner · 8 days
  • Define data ownership, cleansing rules, mandatory fields, duplicate handling, validation thresholds and approval responsibilities by data domainData Migration and Master Data Owner · 6 days
  • Important Define reconciliation rules for opening balances, inventory quantities and values, receivables, payables, assets, CO objects and production master dataCFO and Finance Transformation Lead · 6 days
  • Design the target authorization role architecture, technical users, interface users and segregation-of-duties controlsInformation Security, Internal Controls and Compliance Representatives · 6 days
  • Define transport management, release branching, environment refreshes, test data handling, backup and rollback proceduresSAP Basis and Infrastructure Lead · 5 days
  • Approve detailed interface, migration, reconciliation and architecture specifications for configuration and developmentSAP Program Director / Program Manager · 4 days

Phase 7: S/4HANA Configuration and Development

Week 17–27 · 13 tasks · Owner: SAP Systems Integrator

Configure the S/4HANA core modules and build approved extensions, interfaces, forms, reports, workflows and authorization roles. The phase produces a fully integrated solution suitable for migration rehearsals and formal test cycles.

  • Configure FI/CO for the chart of accounts, ledgers, controlling areas, profit centers, cost centers, asset accounting, allocations, closing and tax requirementsFinance Transformation Lead · 12 days
  • Configure MM for purchasing, source determination, inventory management, valuation, account determination, invoice verification and supplier processesProcurement and Materials Management Lead · 12 days
  • Configure SD for business partners, sales areas, pricing, availability, deliveries, shipping, billing, credit and output processingSales and Distribution Lead · 12 days
  • Important Configure PP for BOMs, routings, work centers, MRP areas, planning parameters, production orders, confirmations and capacity planningProduction Planning and Manufacturing Lead · 14 days
  • Important Configure cross-module integration for procure-to-pay, order-to-cash, plan-to-produce, inventory valuation and financial postingsSAP Systems Integrator · 10 days
  • Build and adapt interfaces for MES, EDI, warehouse systems, banks, tax services, CRM and logistics partnersEnterprise Architecture and Integration Lead · 12 days
  • Configure output forms, invoices, purchase orders, delivery documents, labels, statutory reports and electronic messagesSAP Systems Integrator · 9 days
  • Configure approval workflows for purchasing, invoices, sales exceptions, master data and finance processesSAP Systems Integrator · 6 days
  • Important Build and validate authorization roles, composite roles, technical users and segregation-of-duties controls for corporate and plant usersInformation Security, Internal Controls and Compliance Representatives · 10 days
  • Build operational, financial, production and management reports, including required extracts and reconciliation reportsSAP Systems Integrator · 10 days
  • Schedule and validate critical batch jobs for MRP, interfaces, settlements, allocations, billing, payment processing and period closeSAP Basis and Infrastructure Lead · 6 days
  • Execute the initial technical conversion in the sandbox and establish the transport baseline for configuration, code and integrationsSAP Basis and Infrastructure Lead · 8 days
  • Prepare module-level unit-test scripts, representative master data and controlled test users for all configured processesTest and Quality Manager · 6 days

Phase 8: Data Cleansing and Migration Rehearsals

Week 20–26 · 9 tasks · Owner: Data Migration and Master Data Owner

Improve the quality of master and transactional data and prove the migration approach through repeated trial conversions. Each rehearsal validates transformation logic, load sequencing, reconciliation and the time required for the fiscal-year cutover.

  • Important Profile and cleanse material master data, including descriptions, units of measure, classification, valuation, MRP parameters and duplicate recordsData Migration and Master Data Owner · 9 days
  • Cleanse customer and supplier records, business partner relationships, tax attributes, payment terms, bank data and duplicate accountsData Migration and Master Data Owner · 8 days
  • Cleanse finance and controlling data, including open items, asset records, cost centers, profit centers, internal orders and account assignmentsCFO and Finance Transformation Lead · 9 days
  • Validate BOMs, routings, work centers, production versions, MRP controllers, lead times, lot sizes and plant-specific production master dataProduction Planning and Manufacturing Lead · 11 days
  • Define archival, retention and historical reporting treatment for legacy transactional data that will not be migrated to S/4HANAData Migration and Master Data Owner · 6 days
  • Finalize transformation rules, field mappings, default values, error handling and load sequencing for all approved migration objectsData Migration and Master Data Owner · 7 days
  • Important Execute the first full migration rehearsal, including extraction, transformation, loading, validation, reconciliation and elapsed-time measurementData Migration and Master Data Owner · 10 days
  • Correct migration defects and reconcile record counts, balances, quantities, valuation and key master-data relationships after the rehearsalData Migration and Master Data Owner · 8 days
  • Approve the migration object inventory, quality thresholds, sign-off responsibilities and rehearsal results for the next test cycleSAP Program Director / Program Manager · 4 days

Phase 9: System Integration and End-to-End Testing

Week 28–35 · 11 tasks · Owner: Test and Quality Manager

Validate the converted solution across modules, plants, external systems and operational volumes. Testing focuses on complete business flows rather than isolated transactions, with formal defect control and regression evidence.

  • Prepare the integrated test environment, representative master data, interfaces, test users, batch schedules and traceability matrixTest and Quality Manager · 6 days
  • Test procure-to-pay from requisition and purchase order through goods receipt, invoice verification, payment and FI/CO postingProcurement and Materials Management Lead · 7 days
  • Test order-to-cash from quotation and sales order through availability, delivery, shipment, billing, receivables and revenue recognitionSales and Distribution Lead · 7 days
  • Important Test plan-to-produce from demand and MRP through planned order, production order, material staging, confirmation, goods receipt and settlementProduction Planning and Manufacturing Lead · 10 days
  • Important Test record-to-report, including journal postings, allocations, asset accounting, inventory valuation, period close, reporting and opening-balance reconciliationCFO and Finance Transformation Lead · 8 days
  • Test warehouse, logistics, label, MES, EDI, banking, tax and customer or supplier interface scenarios with positive and negative messagesEnterprise Architecture and Integration Lead · 9 days
  • Important Execute end-to-end scenarios across representative plants, materials, production lines, warehouses, customers, suppliers and fiscal periodsPlant Managers and Business Key Users · 10 days
  • Validate interface monitoring, failed-message reprocessing, background jobs, workflow escalation and operational alertingSAP Basis and Infrastructure Lead · 7 days
  • Execute volume and performance tests for MRP, month-end closing, billing, goods movements, warehouse activity and high-volume interfacesSAP Basis and Infrastructure Lead · 8 days
  • Manage defect triage, severity classification, retesting, regression packs and evidence for all failed scenariosTest and Quality Manager · 10 days
  • Produce the system integration test exit report with outstanding defects, workarounds, retest status and recommendation for UAT entryTest and Quality Manager · 4 days

Phase 10: User Acceptance and Business Validation

Week 36–41 · 8 tasks · Owner: SAP Program Director / Program Manager

Enable business key users and process owners to confirm that the solution supports daily operations, controls, reporting and plant-specific requirements. Formal business acceptance is required before final cutover preparation.

  • Define the UAT plan, acceptance criteria, business scenarios, required evidence and sign-off responsibilities for each process and plantTest and Quality Manager · 5 days
  • Prepare UAT users, role assignments, test data, business scripts and defect-reporting procedures for finance and operational teamsChange, Communications and Training Lead · 6 days
  • Important Execute FI/CO UAT covering daily postings, period close, allocations, assets, reporting, controls and financial reconciliationCFO and Finance Transformation Lead · 8 days
  • Execute MM and SD UAT covering purchasing, inventory, supplier invoices, sales orders, pricing, deliveries, billing and customer processesProcurement and Materials Management Lead and Sales and Distribution Lead · 9 days
  • Execute PP and plant UAT covering MRP, production orders, confirmations, capacity, shop-floor execution and plant reportingProduction Planning and Manufacturing Lead · 9 days
  • Important Execute cross-functional UAT for fiscal-year transition, procure-to-pay, order-to-cash, plan-to-produce and record-to-report scenariosPlant Managers and Business Key Users · 9 days
  • Validate authorization roles, segregation-of-duties controls, audit trails, approval workflows and critical-user accessInformation Security, Internal Controls and Compliance Representatives · 5 days
  • Obtain process-owner sign-off, document accepted workarounds and approve the remaining defect disposition for go-liveSAP Program Director / Program Manager · 5 days

Phase 11: Training and Change Readiness

Week 37–41 · 7 tasks · Owner: Change, Communications and Training Lead

Prepare users and support teams for changed S/4HANA processes, roles and controls. Training is role-based and plant-aware, with key users enabled to support adoption and first-line issue resolution.

  • Map impacted roles, process changes, affected plants, training populations and required competency levelsChange, Communications and Training Lead · 6 days
  • Important Create the role-based curriculum for FI/CO, MM, SD, PP, warehouse, production, management and support usersChange, Communications and Training Lead · 8 days
  • Develop training materials, process simulations, job aids, quick-reference guides, control instructions and fiscal-year close proceduresChange, Communications and Training Lead · 10 days
  • Important Train and certify plant key users, finance super users, procurement leads, sales leads, production planners and service-desk representativesChange, Communications and Training Lead · 8 days
  • Schedule end-user training by role, site, shift and production calendar while maintaining operational coveragePlant Managers and Business Key Users · 5 days
  • Deliver targeted communications covering the go-live date, process changes, business benefits, support channels, freeze periods and user responsibilitiesChange, Communications and Training Lead · 5 days
  • Assess training completion, readiness survey results, open knowledge gaps and availability of local support championsChange, Communications and Training Lead · 6 days

Phase 12: Cutover Planning and Go-Live Rehearsal

Week 42–45 · 7 tasks · Owner: SAP Program Director / Program Manager

Convert the implementation into an executable fiscal-year cutover plan with defined timing, ownership, controls, fallback decisions and support coverage. A full rehearsal validates that the production conversion can be completed within the available year-end window.

  • Important Create the integrated cutover runbook covering system freeze, final extraction, conversion, migration, validation, interface activation, communications and command-center proceduresSAP Program Director / Program Manager · 8 days
  • Define the detailed fiscal-year timetable for final postings, inventory activities, open-item extraction, financial validation, year-end close and first-period openingCFO and Finance Transformation Lead · 6 days
  • Define go/no-go criteria, rollback thresholds, fallback procedures, decision authorities and business continuity actionsExecutive Sponsor / Steering Committee · 4 days
  • Establish cutover staffing, shift coverage, escalation contacts, plant support, vendor availability and command-center communication channelsSAP Program Director / Program Manager · 5 days
  • Important Execute the full go-live rehearsal with timed conversion, migration, interface restart, opening-balance checks, smoke tests and business validationSAP Basis and Infrastructure Lead · 8 days
  • Review rehearsal results, update elapsed times, remove bottlenecks and rebaseline the final cutover sequence and staffing modelSAP Program Director / Program Manager · 5 days
  • Finalize business continuity procedures, transaction freeze communications, manual fallback forms and operational recovery instructionsPlant Managers and Business Key Users · 5 days

Phase 13: Final Migration and Fiscal-Year Go-Live

Week 46–47 · 7 tasks · Owner: SAP Program Director / Program Manager

Execute the controlled production conversion at the fiscal-year boundary, load final data and validate financial, operational and technical readiness. Go-live proceeds only after formal business and technology approval.

  • Important Enforce the transaction freeze, complete final ECC extraction and confirm that all required year-end postings and operational activities are closedCFO and Finance Transformation Lead · 3 days
  • Important Execute the production S/4HANA system conversion, technical post-processing, transports, configuration activation and system availability checksSAP Basis and Infrastructure Lead · 5 days
  • Load final master data, open items, inventory, assets, production data and other approved migration objects according to the cutover runbookData Migration and Master Data Owner · 4 days
  • Validate opening balances, inventory quantities and valuation, receivables, payables, assets, CO objects and production master data against ECC reconciliation reportsCFO and Finance Transformation Lead · 5 days
  • Activate and smoke-test interfaces, EDI messages, batch jobs, workflows, authorizations, forms, reporting and plant-critical transactionsEnterprise Architecture and Integration Lead · 4 days
  • Conduct the formal go/no-go meeting and authorize production release based on cutover evidence, business validation and fallback criteriaExecutive Sponsor / Steering Committee · 1 day
  • Start first-period operations, monitor critical processes and transfer active issues into the hypercare command centerSAP Program Director / Program Manager · 3 days

Phase 14: Hypercare and Stabilization

Week 48–52 · 7 tasks · Owner: SAP Program Director / Program Manager

Stabilize business operations, resolve critical defects and verify performance during the first weeks of live processing. Hypercare ends when operational ownership, support procedures and outstanding issues are formally transferred to business-as-usual teams.

  • Important Operate the hypercare command center with daily triage, severity-based escalation, plant coverage, defect aging and executive reportingSAP Program Director / Program Manager · 15 days
  • Monitor daily finance, procurement, sales, warehouse, MRP, production, interface, batch-job and user-access performance indicatorsSAP Basis and Infrastructure Lead · 12 days
  • Important Resolve critical defects affecting financial postings, opening balances, production planning, customer deliveries, supplier processing or statutory reportingSAP Systems Integrator · 14 days
  • Optimize system performance, background scheduling, MRP runtimes, month-end activities, interfaces and high-volume transaction processingSAP Basis and Infrastructure Lead · 9 days
  • Complete first-period close and reconcile financial statements, inventory valuation, receivables, payables, assets, production variances and management reportingCFO and Finance Transformation Lead · 8 days
  • Transfer solution knowledge, runbooks, monitoring procedures, known errors and support queues to internal IT, service desk and business support teamsSAP Program Director / Program Manager · 6 days
  • Conduct the hypercare exit review, confirm residual-risk ownership, close or transition remaining defects and approve business-as-usual supportCIO or Head of IT · 4 days

Budget

ItemQuantityUnit priceTotal
Program Management, Architecture and Quality Assurance
SAP Program Director60 Person days€950€57,000
PMO and Project Controls Lead70 Person days€700€49,000
Enterprise Architect / Independent QA Reviewer62 Person days€1,000€62,000
SAP Implementation and Custom Code Remediation
S/4HANA Conversion Architect110 Person days€1,200€132,000
FI/CO Functional Consultant Team100 Person days€1,100€110,000
MM and SD Functional Consultant Team175 Person days€1,050€183,750
PP and Manufacturing Functional Consultant110 Person days€1,150€126,500
SAP Basis and Technical Conversion Lead110 Person days€1,050€115,500
ABAP Custom-Code Remediation Team460 Person days€900€414,000
S/4HANA Configuration Team450 Person days€1,050€472,500
Integration, Workflow, Reports and Forms Specialists125 Person days€1,006€125,750
Data Migration, Integration and Testing
Data Migration Lead and Reconciliation Specialist90 Person days€1,000€90,000
Master Data Cleansing Specialists240 Person days€750€180,000
Migration Developers and Integration/EDI Specialists350 Person days€975€341,250
Test Manager and Quality Assurance Lead90 Person days€950€85,500
End-to-End Test Analysts140 Person days€750€105,000
Test Data, Automation and Defect Management Tooling1 Flat rate€38,250€38,250
SAP Software, Infrastructure and Technical Platform
S/4HANA Conversion Licensing and Subscription Changes1 Flat rate€180,000€180,000
Development, Sandbox and Test Environment Hosting12 Person days€15,000€180,000
Production Capacity Expansion, Monitoring and Backup Tooling1 Flat rate€60,000€60,000
Change Management, Training, Cutover and Hypercare
Change and Training Lead100 Person days€950€95,000
Training Content and Key-User Delivery Team1 Flat rate€215,000€215,000
Communications and Adoption Specialist60 Person days€850€51,000
Cutover Management, Go-Live Command Center and Plant Travel1 Flat rate€127,000€127,000
Extended Functional and Technical Hypercare Support100 Person days€1,000€100,000
Sum of items€3,696,000

Risks

Fiscal-Year Cutover and Opening-Balance Failure

High impact

If the final migration, reconciliation or financial validation is not completed within the approved cutover window in Weeks 46–47, incorrect opening balances, incomplete transactions or unavailable interfaces could prevent the first fiscal period from opening and disrupt statutory, management and cash reporting.

Countermeasure: The CFO and Data Migration Lead must define signed reconciliation rules by Week 19, complete at least one timed fiscal-year rehearsal by Week 45, and require the Steering Committee to approve go-live only when FI/CO balances, subledgers, inventory, assets, open items and interfaces meet agreed exit criteria.

Critical Custom-Code Incompatibility

High impact

If ATC findings, simplification items or undocumented custom interfaces remain unresolved after Week 18, obsolete data models, transactions or enhancements may fail during integration testing or production processing.

Countermeasure: The ABAP and Custom Code Lead must complete the code inventory and risk classification by Week 12, remediate or retire all critical objects by Week 18, and provide ATC clearance, unit-test evidence and business-owner sign-off before the solution enters full integration testing.

Master-Data and Migration-Reconciliation Errors

High impact

If material, supplier, customer, asset, production or financial master data does not meet approved quality thresholds by the end of Week 26, migration errors may cause incorrect inventory valuation, procurement, receivables, payables, production planning or financial reporting.

Countermeasure: The Data Migration Lead and named business data owners must establish cleansing rules and ownership by Week 19, perform at least two full migration rehearsals by Week 26, and obtain signed reconciliation of record counts, balances, valuation and key master-data attributes before UAT exit.

Manufacturing Planning and Shop-Floor Disruption

High impact

If bills of material, routings, work centers, MRP parameters, production versions or plant-specific settings are incomplete or incorrectly converted by Week 26, MRP, capacity planning, production orders and shop-floor execution may fail after go-live.

Countermeasure: The Production Planning and Manufacturing Lead, supported by plant key users, must validate critical production master data by Week 24, execute representative plan-to-produce scenarios during Weeks 28–35, and obtain plant-level readiness approval before UAT completion in Week 41.

Integration, EDI and External-System Failure

High impact

If interface mappings and endpoint changes for MES, WMS, EDI partners, banks, tax services, CRM or logistics systems are not validated by Week 35, changed APIs, message formats or certificates may interrupt orders, goods movements, payments, deliveries or statutory submissions.

Countermeasure: The Enterprise Architecture and Integration Lead must baseline all interfaces by Week 8, approve specifications and ownership by Week 19, complete partner and end-to-end testing by Week 35, and verify certificates, monitoring, retry handling and production connectivity during the Week 45 rehearsal.

Insufficient End-to-End and Performance Testing

High impact

If testing remains focused on individual modules or excludes peak volumes, month-end closing, MRP runs, warehouse activity and cross-functional exceptions through Week 35, defects may appear only during UAT, cutover or the first fiscal period.

Countermeasure: The Test and Quality Manager must approve risk-based end-to-end scenarios by Week 28, execute order-to-cash, procure-to-pay, plan-to-produce and record-to-report tests through Week 35, and require performance, batch-window and defect-exit evidence before UAT entry and go-live approval.

Security, Authorization and Segregation-of-Duties Defects

High impact

If converted roles, Fiori access, privileged accounts or segregation-of-duties conflicts are not redesigned and tested before Week 41, users may be unable to perform critical activities or may obtain unauthorized access affecting financial integrity and audit compliance.

Countermeasure: The Information Security and Internal Controls Representatives must define the role and SoD matrix by Week 19, complete role testing and conflict remediation during Weeks 28–41, and require CFO, CIO and control-owner approval of critical access before the Week 45 go-live rehearsal.

Technical Capacity or Conversion-Window Failure

High impact

If infrastructure sizing, database capacity, batch scheduling or conversion performance is inadequate by Week 27, high-volume transactions, MRP, closing activities or the fiscal-year conversion may exceed the available processing window.

Countermeasure: The Basis and Infrastructure Lead must complete sizing and capacity validation by Week 19, run volume and peak-load tests by Week 35, and demonstrate the required backup, restore, conversion and fallback timings during the Week 45 rehearsal.

Scope Growth and ECC-Process Retention

Medium impact

If business units request unapproved ECC customizations or late enhancements after the Week 16 design baseline, solution divergence may increase development effort, consume the reserve and delay testing or fiscal-year readiness.

Countermeasure: The Program Manager and Steering Committee must freeze the approved scope and deviation register at Week 16, route every subsequent request through formal change control, and reject or defer changes that do not have an approved business case, budget, resource and schedule impact.

Specialist-Resource and Vendor-Capacity Constraints

Medium impact

If SAP, ABAP, manufacturing, migration, Basis or testing specialists are unavailable during overlapping Weeks 17–41, configuration, defect resolution and business validation may become bottlenecks and delay the cutover decision.

Countermeasure: The CIO, Program Manager and Systems Integrator must confirm named resources and backup coverage by Week 3, review capacity weekly from Week 10 onward, and secure replacement specialists within five business days when a critical role is forecast to be unavailable.

Inadequate Business Readiness and Training

Medium impact

If role-based training, plant involvement and support preparation are incomplete by Week 41, users may process orders, goods movements, production transactions or financial postings incorrectly and create workarounds after go-live.

Countermeasure: The Change and Training Lead must identify affected roles by Week 16, publish role-based materials and train key users during Weeks 37–41, and require each plant and functional owner to confirm readiness, attendance and support coverage before go-live approval.

Hypercare Overload and Support-Handover Failure

Medium impact

If critical defects, support procedures, monitoring or knowledge transfer remain incomplete at the end of Week 47, the support organization may be unable to resolve incidents during the first close, production cycle or customer billing run.

Countermeasure: The Program Manager and IT Service Owner must establish severity-based support, monitoring and escalation procedures by Week 42, staff extended hypercare for Weeks 48–52, and complete knowledge transfer, service acceptance and open-defect disposition before transition to business-as-usual support.

Stakeholders

Executive Sponsor / Steering Committee

Owns strategic direction, funding, scope escalation, and go-live approval

Involve: Phase 1

CIO or Head of IT

Owns technology strategy, risk acceptance, architecture decisions, and internal IT capacity

Involve: Phase 1

CFO and Finance Transformation Lead

Approves FI/CO design, financial controls, closing processes, opening balances, and audit readiness

Involve: Phase 2

SAP Program Director / Program Manager

Coordinates workstreams, dependencies, milestones, budget, and delivery governance

Involve: Phase 1

External SAP Systems Integrator

Provides S/4HANA conversion expertise, configuration, development, migration, and cutover support

Involve: Phase 1

SAP Basis and Infrastructure Lead

Owns environments, conversion tooling, performance, transport management, backup, and technical operations

Involve: Phase 1

Enterprise Architecture and Integration Lead

Controls interfaces with MES, EDI, warehouse, banking, tax, CRM, and other connected systems

Involve: Phase 2

ABAP and Custom Code Lead

Inventories, prioritizes, remediates, and tests custom developments and extensions

Involve: Phase 3

Procurement and Materials Management Lead

Validates purchasing, inventory, supplier, valuation, and goods-movement processes

Involve: Phase 2

Sales and Distribution Lead

Validates order-to-cash, pricing, delivery, shipping, billing, and customer integration processes

Involve: Phase 2

Production Planning and Manufacturing Lead

Validates MRP, BOMs, routings, production orders, capacity planning, and plant execution

Involve: Phase 2

Data Migration and Master Data Owner

Defines data quality rules, ownership, migration mapping, and reconciliation for master and transactional data

Involve: Phase 3

Test and Quality Manager

Defines test governance, entry/exit criteria, defect management, evidence, and release recommendations

Involve: Phase 3

Plant Managers and Business Key Users

Represent site-specific operational needs and approve end-to-end process readiness

Involve: Phase 4

Change, Communications and Training Lead

Manages communications, role impacts, training delivery, and adoption activities

Involve: Phase 4

Information Security, Internal Controls and Compliance Representatives

Validate access controls, segregation of duties, audit trails, financial controls, and security requirements

Involve: Phase 3

Works Council or Employee Representatives, where applicable

Review affected roles, working practices, and employee-impacting changes

Involve: Phase 4

Obligations and compliance

RequirementOwnerTimingType
Comply with GDPR for employee, customer, supplier and contact data migrated or used in test environments, including lawful processing, data minimization, access control, retention, breach handling and masking of non-production data.Data Protection Officer, Data Migration Lead and Information Security LeadWeeks 2–52Mandatory
Validate FI/CO configuration, opening balances, audit trails, period controls, statutory reports, tax/VAT processing and records retention against applicable local accounting, tax and financial-reporting laws.CFO, Finance Transformation Lead and Tax/Compliance RepresentativesWeeks 9–52Mandatory
Maintain documented internal controls over financial postings, master-data changes, approvals, payment processes, privileged access and segregation of duties, with evidence suitable for internal and external audit.CFO, Internal Controls Representative and SAP Security LeadWeeks 19–52Important
Apply the organization’s information-security policy and relevant ISO 27001-aligned controls, including secure configuration, vulnerability management, encryption, logging, backup/restore, incident response and access recertification.CIO, Information Security Lead and Basis LeadWeeks 3–52Important
Confirm SAP licensing, S/4HANA subscription or maintenance rights, third-party add-on compatibility, interface-provider contracts and EDI partner obligations before production conversion.CIO, Procurement Lead, SAP Licensing Owner and Enterprise Architecture LeadWeeks 1–27Mandatory
Maintain documented backup, disaster-recovery, rollback and business-continuity procedures, and demonstrate recovery and fallback capability before the fiscal-year go-live.Basis and Infrastructure Lead, IT Service Owner and Program ManagerWeeks 19–47Important
Complete formal change-impact consultation with the Works Council or employee representatives where required, covering affected roles, working practices, monitoring and training implications.HR Lead, Change and Training Lead and Works Council LiaisonWeeks 16–41Mandatory
Update the record of processing activities and check whether a data protection impact assessment is needed (GDPR Art. 30, 35)Data protection officer2–4 weeks before go-live (guide value)Mandatory
Sign a data processing agreement with the provider (GDPR Art. 28)Procurement / data protection2–6 weeks before go-live (statutory precondition)Mandatory

Milestones

WeekMilestonePrerequisite
3Approved program charter, governance structure, RACI matrix, integrated delivery plan and confirmed core project teamProgram mobilization and governance
8Approved ECC baseline, application and interface inventory, data-object inventory and signed conversion scopeCurrent-state assessment and scope confirmation
10Approved S/4HANA readiness report, prioritized remediation backlog and technical conversion prerequisitesS/4HANA readiness and technical assessment
16Signed S/4HANA solution blueprint with approved process design, deviations, reporting model, roles and integration principlesFit-to-standard and solution design
18Approved custom-code remediation backlog with completed priority fixes, retired objects, ATC clearance and unit-test evidenceCustom code remediation
19Approved technical architecture, interface specifications, migration design, data ownership model and reconciliation frameworkArchitecture, integration and data migration design
27Configured S/4HANA solution with approved developments, interfaces, reports, workflows, roles and completed module unit-test preparationS/4HANA configuration and development
26Completed migration rehearsal with reconciled results, approved data-quality thresholds and signed migration-object ownershipData cleansing and migration rehearsals
35Completed integration and end-to-end test cycle with agreed defect thresholds, performance evidence and approval to enter UATSystem integration and end-to-end testing
41Signed UAT acceptance by FI/CO, MM, SD, PP and plant process owners with approved defect dispositionUser acceptance and business validation
41Approved training curriculum, trained key-user network, published communications and documented business-readiness assessmentTraining and change readiness
45Approved cutover runbook and successful timed go-live rehearsal meeting conversion, validation and fallback criteriaCutover planning and go-live rehearsal
47S/4HANA live at the start of the fiscal year with reconciled opening balances, active interfaces and formal go-live approvalFinal migration and fiscal-year go-live
52Stable first-period operations, completed financial reconciliation, accepted performance levels and formal transition to business-as-usual supportHypercare and stabilization

How this plan was created

This plan was created by PathHub AI from a single description: “Move from SAP ECC to SAP S/4HANA (brownfield conversion) in a manufacturing company with 900 employees, modules FI/CO, MM, SD and PP, including clean-up of custom code, test cycles, training and hypercare. Go-live at the start of the fiscal year.” Without company context. With your departments, approval processes and compliance requirements it becomes much more precise.

Related documents

The requirements specification usually comes before the project plan. Here is the matching example with Word download.

Obligations

Obligations with lead time: what many think of too late

These obligations are typically triggered by an SAP S/4HANA implementation (example: Germany). PathHub AI schedules them with lead time, warns when the schedule is too tight and shows the rule with its criteria under “Rule & evidence”, which you tick off and back with evidence. Not legal advice.

Update the record of processing activities and check whether a data protection impact assessment is needed (GDPR Art. 30, 35)
Required 2–4 weeks before go-liveguide value
Rule & evidence

Why: The new system processes personal data of customers or employees.

Rule from the compliance library
GDPR (General Data Protection Regulation)
Criteria
  • Legal basis for every processing of personal data (consent, contract, legal obligation, legitimate interest)
  • Complete record of processing activities (Art. 30) for all processes
  • Data Processing Agreements (DPA) with all sub-processors
  • Data Protection Impact Assessment (DPIA) for high-risk processing
  • Technical and organisational measures (TOM) documented

If breached: Fines up to €20 million or 4% of global annual revenue, whichever is higher. Plus civil damages claims by affected individuals.

Evidence: In PathHub you tick off the criteria and attach evidence to each item as a file, link or note. Everything exports as a PDF evidence report.
Sign a data processing agreement with the provider (GDPR Art. 28)
Required 2–6 weeks before go-livestatutory
Rule & evidence

Why: The provider processes personal data on your behalf (cloud, maintenance, support).

Legal basis: GDPR Art. 28: the contract must be in place before processing starts, including tests with real data or data migration.

Rule from the compliance library
Cloud Contract Law
Criteria
  • Data Processing Agreement (DPA) with cloud provider
  • SLA with availability, RPO, RTO
  • Exit and portability clause
  • Data localisation and transfer mechanism (SCC / adequacy)

If breached: Civil claims for data loss; recourse depends on contract. GDPR fines for non-compliance.

Evidence: In PathHub you tick off the criteria and attach evidence to each item as a file, link or note. Everything exports as a PDF evidence report.
Involve the works council and conclude a works agreement on the system (Sec. 87(1) No. 6 BetrVG)
Important 6–12 weeks before go-liveguide value
Rule & evidence

Why: Almost any software logs user actions and is therefore suitable for monitoring performance or behaviour.

Applies: only if a works council exists

Legal basis: Sec. 87(1) No. 6 Works Constitution Act: co-determination for technical systems suitable for monitoring behaviour or performance; suitability is enough. Without agreement the system must not be introduced.

Rule from the compliance library
Works Constitution Act (BetrVG)
Criteria
  • Enable works council election from 5 eligible employees upward
  • Co-determination on working time, monitoring systems, IT rollouts (§87)
  • Hearing before every dismissal (§102): written with reasons
  • Balance-of-interests and social plan on operational changes (§111)

If breached: Dismissals without works council hearing are void. Administrative fines up to €10,000 per violation. Criminal liability (§119) for obstructing the works council up to 1 year imprisonment.

Evidence: In PathHub you tick off the criteria and attach evidence to each item as a file, link or note. Everything exports as a PDF evidence report.
Ensure GoBD process documentation and audit-proof archiving, test e-invoicing
Important 4–8 weeks before go-liveguide value
Rule & evidence

Why: Tax-relevant data must be retained completely, unalterably and auditably, also after the system change.

Applies: if the system processes accounting or tax-relevant data (ERP, invoices, POS)

Rule from the compliance library
GoBD and e-invoicing
Criteria
  • Process documentation for all tax-relevant systems and procedures
  • Complete and unalterable records, changes are logged
  • Retention of tax-relevant documents for the statutory period (generally 8 or 10 years)
  • Data access for tax audits possible (Sec. 147(6) German Fiscal Code)
  • Receipt of structured e-invoices (XRechnung, ZUGFeRD) since 1 Jan 2025
  • Issuing e-invoices to domestic businesses: from 2027 for prior-year turnover above EUR 800,000, from 2028 generally for all (exceptions incl. small-amount invoices, small businesses)

If breached: Formal defects can lead to the bookkeeping being rejected and the tax base being estimated (Sec. 162 German Fiscal Code); refusing data access can trigger a delay penalty (Sec. 146(2c)).

Evidence: In PathHub you tick off the criteria and attach evidence to each item as a file, link or note. Everything exports as a PDF evidence report.
All typical initiatives and their obligations: planning internal projects

Frequently asked questions

How long does an SAP S/4HANA implementation take?
In the example plan, an SAP S/4HANA implementation takes 52 weeks in 14 phases, of which 7 phases partly run in parallel. The actual duration depends on company size, starting point and available resources, with your company context PathHub adjusts the schedule accordingly.
What does an SAP S/4HANA implementation cost?
The example plan estimates about €3,696,000, split into 25 budget line items with quantity and unit price. The largest items are SAP Implementation and Custom Code Remediation, Data Migration, Integration and Testing. This is an AI estimate as a starting point, not a quote.
What are the risks of an SAP S/4HANA implementation?
The plan lists 12 risks with countermeasures. Rated highest: Fiscal-Year Cutover and Opening-Balance Failure; Critical Custom-Code Incompatibility; Master-Data and Migration-Reconciliation Errors.
Who needs to be involved in an SAP S/4HANA implementation?
Among others, the plan includes these people: Executive Sponsor / Steering Committee, CIO or Head of IT, CFO and Finance Transformation Lead, SAP Program Director / Program Manager, External SAP Systems Integrator, SAP Basis and Infrastructure Lead. For each role it states why and from when to involve them.
Can I adapt the plan to my company?
Yes. Open the plan in PathHub without signing up, adjust phases and tasks or describe your own initiative: with company context (departments, approval processes, works council, compliance requirements) every further plan gets more precise.

More project plan examples

Adapt this plan to your company

Open the plan in PathHub: no sign-up. Or describe your own initiative and get a complete plan in minutes.

Open plan →