Example project plan

Project plan for an access control rollout

A project plan for an access control rollout should cover requirements, privacy, employee consultation, procurement, engineering, installation, testing, instruction, and compliance before go-live. This example has nine phases and 49 tasks over 14 weeks, with a budget of approximately €194,500. It includes a DPIA, works agreement, signage, retention rules, and biometric assessment.

  • 14 Weeks
  • 9 Phases
  • 49 Tasks
  • Budget approx. €194,500

No sign-up · opens instantly

Your own project? The AI project plan generator builds a plan like this from a short description.

This is how the plan looks in PathHub. Pick a tab or open the plan live to tick off tasks and edit everything.

app.pathhub.ai/try?example=access-enOpen live
PathHub view “Overview” of the example plan Electronic Access Control and Video Surveillance Implementation
Progress, time, budget, risks and obligations at a glance, plus the next tasks and AI hints.

The plan in detail

Everything in the example plan to read through. In the live plan you can take it over and adapt it.

Phases and tasks

Phase 1: Governance and Mobilization

Week 1 · 3 tasks · Owner: Project Manager / Site Operations Lead

Establish the decision structure, scope, delivery controls and hard compliance gates for the four-month implementation. The phase ensures that the DPIA, works agreement, signage and go-live decision are treated as mandatory dependencies.

  • Important Confirm the Executive Sponsor, Project Manager, workstream leads, decision rights and escalation route for the four-month deliveryExecutive Sponsor / Site Director · 1 day
  • Define the approved scope, including access-controlled doors, surveillance zones, employee groups, visitor processes and the prohibition of unapproved biometric functionalityProject Manager / Site Operations Lead · 2 days
  • Establish the integrated schedule, decision log, risk register, compliance evidence repository and weekly governance meetingsProject Manager / Site Operations Lead · 2 days

Phase 2: Requirements, Site Survey and Process Mapping

Week 2–3 · 5 tasks · Owner: Project Manager / Site Operations Lead

Document the physical, operational, technical and workforce requirements for the logistics site. The outputs will define the permitted surveillance scope and provide the basis for the DPIA, tender and installation design.

  • Survey all relevant pedestrian entrances, vehicle gates, loading areas, emergency exits, staff-only zones and proposed camera locationsFacilities, Security and Health & Safety Team · 4 days
  • Map employee, contractor, visitor, delivery-driver, emergency-access and lost-badge processes across all shiftsSite Operations Lead / Security Team · 3 days
  • Inventory existing door hardware, badge systems, network capacity, power availability, server or cloud constraints and identity-system interfacesIT and Information Security Lead · 4 days
  • Define initial camera privacy zones, masking requirements, prohibited viewing areas and access-log use casesData Protection Officer / Privacy Counsel · 3 days
  • Important Consolidate the functional, technical, privacy, cybersecurity, availability and acceptance requirements into the tender-ready requirements baselineProject Manager / Site Operations Lead · 2 days

Phase 3: DPIA, Legal Basis and Privacy Design

Week 4–5 · 6 tasks · Owner: Data Protection Officer / Privacy Counsel

Complete the GDPR Article 35 assessment and establish the privacy rules that constrain the system design. Purpose limitation, legal basis, retention, access rights, Article 13 information and Article 9 biometric considerations must be resolved before procurement and implementation proceed.

  • Important Conduct and document the GDPR Article 35 DPIA for systematic video surveillance and access-log processing, including processing activities, data flows, necessity, proportionality, risks and mitigation measuresData Protection Officer / Privacy Counsel · 8 days
  • Define and document the purposes, legal basis, retention periods, deletion rules, authorized access roles and prohibited uses for video, access logs and visitor recordsData Protection Officer / Privacy Counsel · 4 days
  • Assess any facial recognition, fingerprint, palm-print or other biometric functionality under GDPR Article 9 and specify that such functionality must remain disabled unless separately justified, approved and legally implementedData Protection Officer / Privacy Counsel with IT and Information Security Lead · 2 days
  • Draft the GDPR Article 13 information concept, including controller details, purposes, legal basis, retention, rights, contact details and the locations and wording of required signsData Protection Officer / Privacy Counsel · 3 days
  • Define procedures for data-subject access requests, objections, deletion requests, surveillance complaints, security incidents and escalation to the DPOData Protection Officer / Privacy Counsel with HR · 2 days
  • Important Obtain formal DPIA approval, document residual risks and record the privacy conditions that must be included in the works agreement, vendor contract and acceptance testsData Protection Officer / Privacy Counsel · 1 day

Phase 4: Works Agreement and Employee Consultation

Week 6–7 · 4 tasks · Owner: HR and Learning & Development with the Works Council

Negotiate the employee-monitoring safeguards and obtain the works agreement required for implementation. The agreement will translate the DPIA and privacy design into binding operational limits for surveillance and access records.

  • Prepare the draft works agreement covering purposes, camera and access-log scope, prohibited performance monitoring, retention, authorized access, employee rights, auditability, complaints and escalationHR and Learning & Development with Data Protection Officer / Privacy Counsel · 3 days
  • Conduct structured consultation sessions with the Works Council and employee representatives, including demonstrations of proposed camera zones and access-record use casesHR and Learning & Development · 5 days
  • Important Resolve open issues on monitoring scope, retention, administrator access, employee information, biometric functionality and change-control rules, then obtain formal approval and signaturesHR and Learning & Development with Works Council · 3 days
  • Convert the signed works agreement into vendor requirements, operating procedures, administrator rules and technical acceptance criteriaProject Manager / Site Operations Lead · 2 days

Phase 5: Tender and Vendor Selection

Week 7–8 · 5 tasks · Owner: Procurement and Finance

Select a security technology vendor capable of delivering access control and video surveillance within the remaining lead time and approved privacy boundaries. Evaluation will cover functionality, cybersecurity, privacy, delivery capability, support and total cost.

  • Important Finalize the tender package and weighted evaluation matrix covering access control, video surveillance, GDPR controls, cybersecurity, availability, support, delivery lead time, installation capacity and total costProcurement and Finance with Project Manager / Site Operations Lead · 2 days
  • Issue the tender, conduct vendor clarification sessions and require written confirmation that biometric features will not be enabled without separate approvalProcurement and Finance · 4 days
  • Evaluate technical, privacy and commercial proposals, including demonstrations of masking, role-based access, audit logs, retention and deletion controlsEvaluation Team led by Project Manager / Site Operations Lead · 5 days
  • Perform vendor due diligence covering security architecture, remote access, cloud hosting, subprocessors, data-processing terms, support response, references and equipment availabilityIT and Information Security Lead with Data Protection Officer / Privacy Counsel · 3 days
  • Important Submit the selection recommendation and obtain sponsor and procurement approval for the preferred vendor and contract awardProcurement and Finance · 1 day

Phase 6: Detailed Engineering and Procurement

Week 9–10 · 6 tasks · Owner: Selected Security Technology Vendor / System Integrator

Translate the approved requirements into an installable technical design and secure the equipment, services and site access needed for delivery. The design must preserve the approved privacy scope and support a controlled installation with minimal logistics disruption.

  • Important Produce and approve detailed camera, reader, controller and privacy-mask layouts, including field of view, no-go zones, emergency routes and approved surveillance purposesSelected Security Technology Vendor / System Integrator with Facilities and Data Protection Officer / Privacy Counsel · 4 days
  • Design the network, segmentation, storage, encryption, identity integration, administrator roles, audit logging, backup and automated deletion architectureIT and Information Security Lead with Selected Security Technology Vendor / System Integrator · 4 days
  • Confirm door hardware adaptations, cabling routes, power requirements, mounting points, fire and emergency-release interfaces and installation constraintsFacilities, Security and Health & Safety Team · 3 days
  • Finalize equipment quantities, software licenses, storage capacity, maintenance terms and purchase orders, then verify delivery dates against the Week 12 installation startProcurement and Finance · 2 days
  • Prepare the installation runbook, shift-by-shift work schedule, rollback procedure, temporary access arrangements and logistics-site continuity planProject Manager / Site Operations Lead with the Vendor · 2 days
  • Prepare the final Article 13 sign artwork and order durable signs for every affected entrance and surveillance zoneData Protection Officer / Privacy Counsel with Facilities · 1 day

Phase 7: Installation and Configuration

Week 11–12 · 10 tasks · Owner: Selected Security Technology Vendor / System Integrator

Install and configure the physical and digital components while maintaining safe logistics operations. Surveillance and access processing must remain within the approved DPIA and works-agreement boundaries, with Article 13 signs installed before any operational activation.

  • Conduct the installation safety briefing, establish work zones and coordinate out-of-hours work around shift changes, loading operations and emergency routesFacilities, Security and Health & Safety Team · 1 day
  • Install readers, controllers, door hardware, cabling, power connections and emergency-release interfaces at approved entry pointsSelected Security Technology Vendor / System Integrator · 5 days
  • Install cameras in approved locations and verify field of view, privacy masks, no-go areas and exclusion of unrelated employee activitySelected Security Technology Vendor / System Integrator with Data Protection Officer / Privacy Counsel · 4 days
  • Deploy and secure servers, appliances or cloud services, including network segmentation, encryption and restricted administrative connectivityIT and Information Security Lead with the Vendor · 3 days
  • Configure employee, contractor, visitor and emergency access profiles, badge rules, approval workflows and least-privilege administrator rolesSecurity Team with IT and Information Security Lead · 3 days
  • Configure recording schedules, camera masking, approved retention periods, automated deletion and storage protectionSelected Security Technology Vendor / System Integrator with Data Protection Officer / Privacy Counsel · 3 days
  • Configure audit logs, security alerts, administrator activity logging, remote-support restrictions and account disablement proceduresIT and Information Security Lead · 2 days
  • Important Install GDPR Article 13 information signs at all affected entrances and surveillance zones before system activation, and record photographic evidence of placement and visibilityFacilities with Data Protection Officer / Privacy Counsel · 2 days
  • Complete connectivity, door-safety, emergency-release and basic camera-view checks without disrupting live logistics flowsSelected Security Technology Vendor / System Integrator with Health & Safety Team · 1 day
  • Create the as-built drawings, device inventory, configuration baseline and credentials handover packageSelected Security Technology Vendor / System Integrator · 2 days

Phase 8: Acceptance, Signage, Training and Readiness

Week 12–13 · 6 tasks · Owner: Project Manager / Site Operations Lead

Validate the system technically, operationally and from a privacy perspective, then prepare all employees and administrators for controlled use. No go-live may occur unless the DPIA conditions, signed works agreement, Article 13 signage and acceptance criteria are all verified.

  • Execute technical acceptance tests for door operation, badge issuance, camera recording, image quality, network resilience, alerts, administrator roles and emergency releaseSelected Security Technology Vendor / System Integrator with IT and Security Team · 4 days
  • Important Execute privacy and compliance acceptance tests for approved purposes, camera masking, access permissions, retention, automated deletion, audit logs, Article 13 sign visibility and data-subject request handlingData Protection Officer / Privacy Counsel · 4 days
  • Test deletion from primary storage, backups and exports, and retain evidence showing that video and access records are deleted according to the approved retention scheduleIT and Information Security Lead with the Vendor · 2 days
  • Train security administrators and shift supervisors on badge enrollment, visitor handling, lost badges, incident escalation, permitted searches, access requests and prohibited employee monitoringHR and Learning & Development with Security Team · 3 days
  • Important Deliver employee instruction across all shifts for the 300 affected employees, including badge procedures, camera purposes, Article 13 information, privacy contacts and the works-agreement safeguardsHR and Learning & Development · 4 days
  • Important Prepare the go-live decision pack and confirm closure or formal acceptance of defects, DPIA conditions, works-agreement obligations, signage evidence, training coverage and support readinessProject Manager / Site Operations Lead with Executive Sponsor / Site Director · 2 days

Phase 9: Go-Live and Hypercare

Week 14 · 4 tasks · Owner: Project Manager / Site Operations Lead

Launch the access control and video surveillance system under controlled operational monitoring and resolve early defects quickly. The phase transfers ownership to site operations while preserving compliance evidence and support arrangements.

  • Important Execute the controlled go-live, activate approved access and surveillance functions, staff the support channel across shifts and monitor the first operational cyclesProject Manager / Site Operations Lead with Security Team and Vendor · 2 days
  • Verify live access events, camera operation, administrator audit trails, retention/deletion jobs, incident escalation and handling of employee or data-subject requestsIT and Information Security Lead with Data Protection Officer / Privacy Counsel · 2 days
  • Resolve priority defects, access failures, camera blind spots or operational issues and document any residual issues with owners and due datesSelected Security Technology Vendor / System Integrator · 2 days
  • Complete operational handover of procedures, system inventory, support contacts, DPIA evidence, works agreement, training records, signage evidence and hypercare backlogProject Manager / Site Operations Lead · 1 day

Budget

ItemQuantityUnit priceTotal
Internal Personnel
Project Manager / Site Operations Lead16 Person days€900€14,400
IT and Information Security Lead7 Person days€800€5,600
Facilities, Security, Health & Safety and Shift Operations Representatives6 Person days€725€4,350
HR and Learning & Development Lead5 Person days€650€3,250
Procurement and Finance Coordinator4 Person days€600€2,400
External Privacy, Legal and Procurement Services
DPIA, legal basis, purpose limitation, retention and GDPR Article 9 biometric assessment12 Person days€1,200€14,400
Works agreement negotiation and employee-monitoring legal support6 Person days€950€5,700
Site survey, access-point mapping and operational process analysis6 Person days€900€5,400
Tender preparation, vendor demonstrations and commercial evaluation4 Person days€900€3,600
Independent security architecture and privileged-access review1 Flat rate€900€900
Software, Licenses and Equipment
Access control and video management software licenses1 Flat rate€14,000€14,000
Network video recorder and compliant storage capacity for approved retention periods1 Flat rate€14,000€14,000
IP surveillance cameras for approved security zones32 Person days€600€19,200
Electronic access card readers16 Person days€850€13,600
Door controllers and access-control panels5 Person days€1,400€7,000
Employee and contractor access badges350 Person days€8€2,800
PoE switches, UPS equipment, firewall adaptation and monitoring console hardware1 Flat rate€8,600€8,600
Installation, Integration and Testing
Structured cabling, mounting, electrical work and door hardware adaptations1 Flat rate€18,000€18,000
Vendor installation and commissioning labor across operational shifts18 Person days€850€15,300
System configuration, identity integration, role-based access, retention and deletion controls5 Person days€900€4,500
Technical, privacy and operational acceptance testing with defect correction2 Person days€900€1,800
Training, Transparency and Operational Readiness
GDPR Article 13 information signs: design finalization, production and mounting before go-live40 Person days€120€4,800
Employee shift briefings covering badge use, surveillance purposes, privacy rights and procedures16 Person days€250€4,000
Security administrator and nominated supervisor training2 Person days€900€1,800
Operating procedures, incident handling, handover documentation and first-week hypercare coordination1 Flat rate€5,100€5,100
Sum of items€194,500

Risks

DPIA or Works Agreement Delay

High impact

If the DPIA is not approved by the end of Week 5 or the works agreement remains unresolved after Week 7, the project may be unable to lawfully or organizationally proceed to installation, employee instruction or Week 14 go-live.

Countermeasure: The DPO will begin the DPIA evidence collection in Week 1, and HR will schedule works council sessions in Week 1. The Sponsor will enforce approval gates at the end of Weeks 5 and 7 and prohibit go-live without both approvals.

Excessive or Unclear Surveillance Scope

High impact

If the site survey or later security requests expand camera coverage to welfare areas, neighboring property, public areas, or broad employee movement tracking after the privacy design is approved, the processing may exceed its defined purpose and require redesign.

Countermeasure: Facilities, Security and the DPO will approve a documented privacy zoning plan by the end of Week 3. The Project Manager will require written DPO approval for any scope change before the Week 10 design freeze.

Invalid Article 13 Transparency and Signage

High impact

If signs are missing, incomplete, obscured, incorrectly positioned or installed after cameras begin operating, employees, visitors and contractors may not receive the required information before their data is collected.

Countermeasure: The DPO will approve the layered Article 13 notice by Week 5; Facilities will install signs at every relevant entry and surveillance zone by Week 11, at least three weeks before the Week 14 go-live; the Project Manager will record a site-wide signage verification in Week 13.

Biometric Feature Creep

High impact

If a vendor proposes facial recognition, fingerprint readers, biometric templates or another biometric feature before the Week 10 design freeze, the project may trigger GDPR Article 9 requirements, additional employee consultation and a significant redesign.

Countermeasure: The DPO and IT Security Lead will document the Article 9 decision by Week 5 and prohibit biometric functionality unless separately approved. Procurement will include a no-undisclosed-biometric-feature clause in the contract by Week 8.

Hardware or Installation Lead-Time Slippage

High impact

If the vendor is not awarded by Week 8, equipment is not confirmed by Week 10, or door hardware, cabling or installation resources are unavailable, the three-week installation window may be insufficient for Week 14 go-live.

Countermeasure: Procurement and Finance will complete the award by Week 8, obtain written delivery commitments by Week 9 and maintain approved alternative equipment. The Vendor and Facilities Lead will complete a readiness review before installation starts in Week 11.

Operational Disruption and Unsafe Installation

High impact

If installation affects loading bays, shift changes, pedestrian or vehicle routes, emergency exits, or access to operational areas during peak periods in Weeks 11–12, the work may cause safety incidents, shipment delays or unauthorized bypasses.

Countermeasure: Facilities, Health & Safety and Site Operations will approve a phased installation and traffic-management plan by Week 10. The vendor will perform high-disruption work outside peak shifts, maintain temporary access controls and test emergency egress before each affected area is reopened.

Cybersecurity or Unauthorized Administrative Access

High impact

If default credentials, excessive administrator privileges, insecure remote support, unsegmented camera networks or exposed cloud interfaces remain during configuration or acceptance in Weeks 12–13, attackers or unauthorized staff could access footage or alter entry permissions.

Countermeasure: The IT and Information Security Lead will require MFA, unique accounts, least-privilege RBAC, network segmentation, encrypted communications, restricted vendor access and audit logging before acceptance in Week 13. Security testing and credential review will be mandatory go-live gates.

Inadequate Retention and Deletion Controls

High impact

If video, access logs, exports or backups are retained beyond the approved periods, automated deletion fails, or administrators can alter retention settings during Weeks 12–13, the project may breach purpose limitation and storage limitation requirements.

Countermeasure: The DPO and IT Lead will define retention and deletion rules by Week 5. The vendor will configure them by Week 12, and IT will execute documented deletion, backup and restoration tests in Week 13 before the Sponsor approves go-live.

Employee Resistance or Perceived Performance Monitoring

Medium impact

If employees believe access records or video will be used for performance management, or if fewer than 95% of affected employees complete instruction by the end of Week 13, staff may resist the system, share badges or bypass procedures.

Countermeasure: HR, the Works Council and Operations will publish the permitted and prohibited uses by Week 7, provide shift-based training during Weeks 12–13 and track completion. The Site Operations Lead will provide a staffed query and escalation process during the first two weeks after go-live.

Integration, Reliability or Emergency Access Failure

Medium impact

If access readers fail during network outages, identity synchronization is inaccurate, camera recording is unavailable, or emergency override testing fails during Week 13 acceptance, employees may be locked out or the site may lose security coverage.

Countermeasure: IT, the vendor and Site Operations will define availability, fail-safe and fail-secure requirements by Week 10. They will test offline access, emergency release, backup power, identity synchronization and incident recovery in Week 13, with manual fallback procedures documented before go-live.

Unplanned Site-Work or Contract Cost Overrun

Medium impact

If surveys identify unexpected cabling, power, door hardware, network or storage requirements after the Week 10 design approval, costs may exceed the EUR 220,000 budget or require scope reductions that weaken security or privacy controls.

Countermeasure: Procurement, Finance and Facilities will complete a measured site survey and costed bill of materials by Week 3, retain the EUR 26,400 reserve for approved changes and require Sponsor approval for any forecast exceeding the approved budget.

Stakeholders

Executive Sponsor / Site Director

Owns the business case, authorizes funding, accepts residual risks and makes the final go-live decision.

Involve: From Phase 1 through governance reviews and final go-live approval

Project Manager / Site Operations Lead

Coordinates the schedule, dependencies, operational constraints, acceptance activities and handover.

Involve: From Phase 1 through hypercare and project closure

Works Council

Represents employee interests and negotiates binding provisions for monitoring, access records, retention and prohibited uses.

Involve: From Phase 1, with intensive involvement during Phases 3–4 and readiness review

Data Protection Officer / Privacy Counsel

Leads the DPIA, confirms the legal basis, defines retention and access controls, prepares Article 13 information and evaluates any biometric processing.

Involve: From Phase 1 through privacy acceptance and post-go-live verification

IT and Information Security Lead

Defines network, identity, storage, logging, cybersecurity, integration and privileged-access requirements.

Involve: From Phase 2 through design, configuration, testing and handover

Facilities, Security and Health & Safety Team

Defines physical security requirements, validates camera and reader locations and protects emergency and logistics operations during installation.

Involve: From Phase 2 through site survey, engineering, installation and acceptance

HR and Learning & Development

Manages employee communications, instructions, administrator training and responses to workforce questions.

Involve: From Phase 4 through training, readiness and hypercare

Procurement and Finance

Runs the tender, evaluates commercial terms, controls purchase orders and confirms affordability and contractual protections.

Involve: From Phase 2 through vendor award and procurement completion

Selected Security Technology Vendor / System Integrator

Designs, supplies, installs, configures, tests and documents the technical solution and provides initial support.

Involve: From Phase 5 through installation, acceptance and hypercare

Employees, Shift Supervisors and Operational Representatives

Validate shift-based access needs, usability, workforce communications and the effect on daily logistics processes.

Involve: From Phase 2 through consultation, testing, instruction and go-live

Obligations and compliance

RequirementOwnerTimingType
Complete and approve a GDPR Article 35 DPIA for the systematic video surveillance and access-control processing before implementation and go-live; document risks, safeguards, residual risk and approval evidence.Data Protection Officer / Privacy Counsel3–6 weeks before go-live (statutory precondition)Mandatory
Define and document the GDPR Article 6 legal basis, specific security purposes, prohibited uses, data fields, access-log use, retention periods and deletion rules for video and access records.Data Protection Officer / Privacy Counsel with Site Security and ITWeeks 2–5; configure and test in Weeks 9–13Mandatory
Assess whether facial recognition, fingerprints, templates or other biometric functionality is proposed; prohibit it unless a separate GDPR Article 9 assessment, lawful condition and required safeguards are approved.Data Protection Officer / Privacy Counsel with Procurement and ITWeeks 3–5; recheck at vendor award and design freeze in Weeks 8–10Mandatory
Prepare and deploy complete GDPR Article 13 information notices and visible surveillance signs before any recording or monitoring begins, including controller identity, purposes, legal basis, retention, rights and contact details.Data Protection Officer / Privacy Counsel and FacilitiesDesign in Weeks 4–5; print and install by Week 11; verify in Week 13 before Week 14 go-liveMandatory
Obtain the approved works agreement and complete employee consultation covering monitoring scope, permitted purposes, access to records, retention, employee rights, escalation and prohibited performance-monitoring uses.HR / Learning & Development and Works CouncilWeeks 1–7; conditions incorporated into vendor contract and operating procedures by Week 8Mandatory
Implement GDPR Article 32 technical and organizational measures, including MFA, least privilege, role-based access, network segmentation, encryption, audit logs, secure remote support, vulnerability management and tested retention/deletion controls; align controls with the internal information-security policy and ISO/IEC 27001 principles where applicable.IT and Information Security Lead with VendorDesign Weeks 6–10; implementation and testing Weeks 11–13Mandatory
Maintain lawful site-operation controls for logistics areas, including emergency egress, fire and evacuation routes, safe installation, temporary access arrangements, visitor/contractor procedures and documented incident and data-subject request handling.Facilities, Health & Safety, Site Operations and DPOSite survey Weeks 2–3; procedures and testing Weeks 9–13; ongoing after go-liveImportant

Milestones

WeekMilestonePrerequisite
1Approved project charter, governance structure and 16-week critical-path plan with DPIA, works agreement and go-live gates identified.Sponsor appointment, core team availability and initial scope confirmation
3Approved site survey, process maps, initial privacy zoning plan and tender-ready requirements baseline.Approved project charter and access to the site, systems and operational representatives
5Approved GDPR Article 35 DPIA, documented legal basis and retention model, Article 13 information design, and recorded Article 9 biometric decision.Requirements baseline, monitoring purposes, data-flow details and privacy zoning plan
7Signed works agreement with no unresolved conditions preventing system installation or employee instruction.DPIA findings, proposed monitoring scope, retention rules and employee consultation
8Approved vendor award, commercial decision record and contract conditions incorporating the DPIA and works agreement.Tender-ready requirements, vendor submissions and sufficiently settled works-agreement conditions
10Approved detailed design, confirmed equipment delivery, installation runbook and printed Article 13 signage available for deployment.Vendor award, signed contract, approved privacy controls and site engineering data
12Installed and configured system, Article 13 signs in place at least three weeks before Week 16 go-live, and documented installation baseline completed.Approved detailed design, delivered equipment, site access and installation windows
13Signed technical, privacy and operational acceptance records; all Article 13 signs verified; employee and administrator instruction completed; go-live approval pack ready.Installed system, completed testing, approved procedures, signage and training materials
14System live for all approved users and zones, first-week operational checks completed, priority defects controlled and formal handover to site operations accepted.Go-live approval, completed acceptance, trained users and administrators, and operational support readiness

How this plan was created

This plan was created by PathHub AI from a single description: “Introduce an electronic access control system with video surveillance at the site of a logistics company with 300 employees: vendor selection, data protection impact assessment, works agreement, installation and instruction. Go-live in four months.” Without company context. With your departments, approval processes and compliance requirements it becomes much more precise.

Obligations

Obligations with lead time: what many think of too late

These obligations are typically triggered by an access control rollout (example: Germany). PathHub AI schedules them with lead time, warns when the schedule is too tight and shows the rule with its criteria under “Rule & evidence”, which you tick off and back with evidence. Not legal advice.

Carry out a DPIA, define purpose and retention, put up information signs (GDPR Art. 13, 35)
Required 3–6 weeks before go-livestatutory
Rule & evidence

Why: Monitoring strongly affects the privacy of employees and visitors.

Legal basis: GDPR Art. 35: systematic monitoring requires a prior DPIA; signs/information under Art. 13 before going live. Biometric data is specially protected (Art. 9).

Rule from the compliance library
GDPR (General Data Protection Regulation)
Criteria
  • Legal basis for every processing of personal data (consent, contract, legal obligation, legitimate interest)
  • Complete record of processing activities (Art. 30) for all processes
  • Data Processing Agreements (DPA) with all sub-processors
  • Data Protection Impact Assessment (DPIA) for high-risk processing
  • Technical and organisational measures (TOM) documented

If breached: Fines up to €20 million or 4% of global annual revenue, whichever is higher. Plus civil damages claims by affected individuals.

Evidence: In PathHub you tick off the criteria and attach evidence to each item as a file, link or note. Everything exports as a PDF evidence report.
Check and document lawfulness under the BDSG (publicly accessible areas, employee data)
Required 2–4 weeks before go-livestatutory
Rule & evidence

Why: Additional national limits apply to employees and publicly accessible areas.

Legal basis: Sec. 4 BDSG governs video surveillance of publicly accessible areas, Sec. 26 the processing of employee data; covert or permanent performance monitoring is generally not permitted.

Rule from the compliance library
Federal Data Protection Act (BDSG)
Criteria
  • Data protection officer appointed (20+ employees with regular data processing)
  • Employee data protection: data minimisation + purpose limitation in HR
  • Video surveillance with signage and stated purpose
  • Works council involvement for HR data processing

If breached: Fines up to €50,000 for violations of BDSG §§41-43. GDPR fines (up to €20m / 4%) apply in parallel.

Evidence: In PathHub you tick off the criteria and attach evidence to each item as a file, link or note. Everything exports as a PDF evidence report.
Conclude a works agreement on the monitoring technology
Important 6–12 weeks before go-liveguide value
Rule & evidence

Why: Without agreement with the works council the technology must not be used.

Applies: only if a works council exists

Legal basis: Sec. 87(1) No. 6 BetrVG: cameras, tracking and access systems are typical technical monitoring systems.

Rule from the compliance library
Works Constitution Act (BetrVG)
Criteria
  • Enable works council election from 5 eligible employees upward
  • Co-determination on working time, monitoring systems, IT rollouts (§87)
  • Hearing before every dismissal (§102): written with reasons
  • Balance-of-interests and social plan on operational changes (§111)

If breached: Dismissals without works council hearing are void. Administrative fines up to €10,000 per violation. Criminal liability (§119) for obstructing the works council up to 1 year imprisonment.

Evidence: In PathHub you tick off the criteria and attach evidence to each item as a file, link or note. Everything exports as a PDF evidence report.
All typical initiatives and their obligations: planning internal projects

Frequently asked questions

How long does an access control rollout take?
In the example plan, an access control rollout takes 14 weeks in 9 phases, of which 2 phases partly run in parallel. The actual duration depends on company size, starting point and available resources. With your company context PathHub adjusts the schedule accordingly.
What does an access control rollout cost?
The example plan estimates about €194,500, split into 25 budget line items with quantity and unit price. The largest items are Software, Licenses and Equipment, Installation, Integration and Testing. This is an AI estimate as a starting point, not a quote.
What are the risks of an access control rollout?
The plan lists 11 risks with countermeasures. Rated highest: DPIA or Works Agreement Delay; Excessive or Unclear Surveillance Scope; Invalid Article 13 Transparency and Signage.
Who needs to be involved in an access control rollout?
Among others, the plan includes these people: Executive Sponsor / Site Director, Project Manager / Site Operations Lead, Works Council, Data Protection Officer / Privacy Counsel, IT and Information Security Lead, Facilities, Security and Health & Safety Team. For each role it states why and from when to involve them.
Can I adapt the plan to my company?
Yes. Open the plan in PathHub without signing up, adjust phases and tasks or describe your own initiative: with company context (departments, approval processes, works council, compliance requirements) every further plan gets more precise.

More project plan examples

Adapt this plan to your company

Open the plan in PathHub: no sign-up. Or describe your own initiative and get a complete plan in minutes.

Open plan →